Power & Energy

Power & Energy

Power, Site & Energy Migration

Power — not silicon — now governs where, how and at what cost AI factories get built. This watch brings together the live power picture, live site intelligence, a research framework for energy-driven workload migration, and the placement logic that connects them.

Read the power signals first, then use site intelligence and placement logic to turn them into a location and workload decision.

Module 1 · Power Watch

Current grid, power price, connection, generation and procurement signals. Power — not silicon — now governs where, how, and at what cost AI factories get built.

+17%

U.S. DC demand growth 2025

AI-focused facilities surging +50%

~1/3

Behind-the-meter share

Of new U.S. capacity as energy islands

30–50%

Pipeline under construction

Of announced capacity actively building

49 GW

Persistent shortfall

Could persist through 2028

95%+

Nuclear capacity factor

Firm baseload, locked for 20 years

~$1.15tn

Hyperscaler capex 2025–27

Goldman Sachs estimate (CLM-TCO-006)

Data

The demand & supply picture

Global data-center electricity demand

TWh · ~415 in 2024 to a projected 1,200 by 2035

Lead times: compute moves in months, the grid in years

Years from request to delivery

The nuclear pivot: gigawatt baseload locked up

Target nuclear capacity by buyer (GW)

Tightening EU efficiency mandates

Target PUE (lower is better)

Deals

Nuclear PPAs: firm baseload, 20-year horizons

The largest buyers have converted nuclear into multi-GW baseload procurement.

BuyerCounterpartyCapacityTypeTimeline
MetaVistra (Perry, Davis-Besse, Beaver Valley)>2.6 GW20-yr PPAs, existing plantsBegins late 2026; full by 2034
MetaTerraPower (Natrium)up to 2.8 GW + 1.2 GW storageSodium fast reactorsPower by 2032; target 2035
MetaOklo (Pike County, Ohio)up to 1.2 GWAdvanced nuclear campusPhase 1 2030; full 2034
MetaConstellation (Clinton, IL)1.1 GWExisting plantJune 2025 agreement
MicrosoftConstellation (Three Mile Island)Unit 1 restart20-yr PPA, restart—
GoogleKairos Power (KP-FHR SMRs)up to 500 MWSMRsFirst reactor ~2030; 500 MW by 2035
Analysis

Inside the power crisis

More than 2,060 GW of proposed generation and storage capacity was seeking U.S. grid interconnection at the end of 2025 — more than the country’s entire installed power capacity. Queue capacity does not represent delivered power: most projects will not reach operation, so the queue signals demand and grid strain, not power available to AI factories. Ohio utilities were forced to pause new interconnections entirely. Compute hardware cycles monthly while grid infrastructure plans on a decadal horizon: facility construction takes 2–3 years, but utility-scale transmission and generation take 5–10+ years, with large high-voltage transformer lead times exceeding 2 years.

Latest update in power & grid

Manually reviewed developments in grid capacity and connection. Each card carries its source, publication and verification dates, and an evidence receipt.

Grid and powerVerifiedGlobal2026-Q1

IEA projects global data-centre electricity toward ~945 TWh by 2030

Latest update

The IEA projects global data-centre electricity consumption rising from about 415 TWh in 2024 toward roughly 945 TWh by 2030, replacing the earlier '1,000 TWh by 2026' framing.

Why it matters

The corrected trajectory sets a realistic horizon for AI-driven electricity demand and grid planning.

SourceIEA
Published 2026-Q1Verified 28 July 2026
Grid and powerVerifiedEurope2026-Q1

European hyperscalers pivot to firm nuclear and hydro power

Latest update

European data-centre power is projected to more than double by 2030, with Ireland already near a fifth of national electricity and hyperscalers turning to nuclear and hydro procurement.

Why it matters

Firm-power procurement and power-rich regions are becoming placement differentiators in Europe.

SourceIEA
Published 2026-Q1Verified 28 July 2026
Grid and powerVerifiedUnited States31 December 2025

LBNL Queued Up 2026 records 2,060+ GW seeking US interconnection

Latest update

Lawrence Berkeley National Laboratory's Queued Up 2026 edition reports more than 2,060 GW of proposed generation and storage capacity seeking US grid interconnection at the end of 2025.

Why it matters

It quantifies how large the US interconnection backlog is, but as generation and storage queue capacity — not delivered power and not a data-centre load queue.

Published 2026-Q1Verified 28 July 2026

Turn these signals into a placement decision