Build
Where factories rise.

Frontier AI data centers and construction activity
Data center sites in Texas, California, and New York
Select Texas, California, or New York to see its queued generation capacity, project count, and full market view.
Operating data centers in the US
Frontier AI data centers in the US
The largest AI campuses in the US, with each one’s owner, current power, and latest reported construction progress.
| Site | Owner | Power | State | Latest construction note |
|---|---|---|---|---|
| Anthropic-Amazon New Carlisle | Amazon | 1,037 MW | IN | Buildings 19-32 are operational. This is an estimate based on how long Buildings 1-16 took to become operational. In May 2026, the foundatio |
| Colossus 2 | SpaceXAI | 946 MW | TN | Building 3 is estimated to be completed. The site is predicted to have enough power infrastructure installed for a total of 1.5 GW of IT Pow |
| OpenAI Stargate Abilene | Oracle | 824 MW | TX | Buildings 7-8 are estimated to be operational. On March 24, Building 8 roughly looked like where Building 3 was in September. Building 3 is |
| Microsoft Fairwater Atlanta | Microsoft | 636 MW | GA | Building 3 and 4 are operational. |
| Meta Prometheus | Meta | 471 MW | OH | Buildings 22-27 (3rd set of 6 Meta tents) are operational. This is a conservative estimate to align with the operability of the [Socrates th |
| Microsoft Fairwater Wisconsin | Microsoft | 369 MW | WI | Buildings 3-11 are estimated to be operational. The grading for this revised 9-building plan was underway in May 2026, and we assume an aver |
| Google Pryor (North) | 368 MW | OK | Building 2 is operational, confirmed via RAAD drone imagery of spinning cooling tower fans on September 8th. | |
| Colossus 1 | SpaceXAI | 340 MW | TN | No major changes to the data center since February. Solar panels have been placed next to the facility. |
| Google New Albany | 333 MW | OH | Building 5 has all cooling towers installed, and all other components look complete, but there is still light work around the building. Base | |
| Google Columbus | 303 MW | OH | Building 5 operational. The [transmission line construction notice](https://www.aeptransmission.com/ohio/docs/Hartman%20Farms%20Extension%20 | |
| Amazon Madison Mega Site | Amazon | 284 MW | — | Buildings 8-12 are operational. In June of 2026 only a faint outline of buildings 10,11 and 12 is visible, estimating construction completio |
| CoreWeave Denton TX | CoreWeave | 262 MW | TX | Building 8 projected operational. [TDLR project TABS2026028247](https://www.tdlr.texas.gov/TABS/Projects/TABS2026028247) schedules Building |
| QTS Richmond 1 | 238 MW | VA | No changes to the site since December 2025. | |
| Google Bristow | 238 MW | VA | Building 3 is operational, based off of colored motion artifacts from cooling towers. | |
| Google Papillion | 237 MW | — | Building 4 shell mostly complete, Building 5 steel framing is underway. | |
| Google Council Bluffs (East) | 237 MW | IA | Building 3 is operational. 7 cooling towers were finally installed despite being more spread out compared to the first two buildings. Coolin | |
| Google Omaha | 237 MW | NE | Building 5 is operational. We expect a 5th building because there's enough land cleared for one. We assume a roughly 6-month delay after Bui | |
| Amazon Ridgeland | Amazon | 228 MW | — | Buildings 6-14 are operational (estimate). Buildings 1-4 took an estimated 2.25 years on this site. We assume Buildings 6-14 get underway by |
| AWS New Albany | Amazon | 213 MW | — | Expected operational date for the remaining tracked buildings (11, and 1-4) across the three campuses. This estimate is based on the previou |
| Anthropic Lake Mariner | AI XPV Platform | 210 MW | NY | Building 3 (AKA CB5) is operational. On February 26, 2026, Terawulf [stated](https://investors.terawulf.com/news-events/press-releases/detai |
| Microsoft Goodyear | Microsoft | 202 MW | AZ | Foundations appear to be underway for Building 5 and 6, just north of Building 4. |
| Microsoft Project Osmium | Microsoft | 190 MW | IA | No notable changes since October. |
| Google Mesa | 183 MW | — | Building 2 is operational. This is estimated based on the close-to-complete construction status from May 2026. | |
| QTS Richmond 2 | 180 MW | VA | Building 5 is estimated to be operational, based on the previous entry. | |
| Meta-QTS Hillsboro 2 | Meta | 180 MW | OR | All four buildings are operational. |
Epoch AI, Frontier Data Centers · CC BY 4.0.
Data center permitting and public sentiment
Air permits, environmental review, local moratoria, and public sentiment can impact a data center even if it already has a path to power.
Permitting and community signals
Data center records in public permitting registers.
Of the 15 data centers with a Clean Air Act permit, 12 are in Texas, and all 12 are Title V major sources; 2 are in California, and 1 is in New York.
CEQAnet, data center environmental filings · California public record; EPA ECHO, data center air permits · Nov 23, 2026 · Public domainCalifornia data center environmental review
California’s environmental review law (CEQA) requires public agencies to review discretionary projects, and CEQAnet publishes the filings. These are the latest filings that affect data centers, showing local moratoria and how far individual projects have progressed.
| Filed | Project or rule | County | Stage | What it means |
|---|---|---|---|---|
| 01 Oct 2026 | Extension of Uncodified Urgency Interim Ordinance No. 3669 - Temporary Moratorium on New Data Center Development | Tulare | Moratorium | A county or city has paused new data center development. |
| 01 Oct 2026 | Extension of Interim Urgency Ordinance No. 2134 | Riverside | Moratorium | A county or city has paused new data center development. |
| 31 Aug 2026 | Ordinance imposing a temporary moratorium on Data Centers | Calaveras | Moratorium | A county or city has paused new data center development. |
| 28 Aug 2026 | Ordinance No. 821, to Establish an Ordinance adding Chapter 17.42 – Artificial Intelligence (AI) Data Centers & Associated Uses to the Irwindale Municipal Code. | Los Angeles | Exempt | Exempt from environmental review, typically a small project, rule change, or lease. |
| 19 Aug 2026 | San Jose Data Center | Santa Clara | Approved | The local agency has approved the project; it can move on to permits and construction. |
| 05 Aug 2026 | Vernon Backup Generating Facility | Los Angeles | Review starting | A full environmental study is about to begin, so the project is at an early stage. |
| 28 Jul 2026 | Second Amendment to the Riverside County Information Technology Department (RCIT) Chicago Lease Agreement with JS MCA Hunter Park LP, Riverside | Riverside | Exempt | Exempt from environmental review, typically a small project, rule change, or lease. |
| 21 Jul 2026 | San Jose Data Center | Santa Clara | Approved | The local agency has approved the project; it can move on to permits and construction. |
| 21 Jul 2026 | Northtown Backup Generating Facility | Santa Clara | Review starting | A full environmental study is about to begin, so the project is at an early stage. |
| 16 Jul 2026 | SP25-029 and ER25-243 300 Holger Way Data Center Project | Santa Clara | Exempt | Exempt from environmental review, typically a small project, rule change, or lease. |
Latest 10 of 60 filings since 2021. Each title links to its filing on CEQAnet · California public record
US data center construction spending
Private data center construction put in place each month from 2014 (annualized). Seasonally adjusted annual rate, USD bn.
Census C30, data center construction spending · Public domainLatest data center construction and permitting changes
Campus milestones, local ordinances, and queue changes from the last 120 days, newest first.
Latest changes
Last 120 days: 26 campus milestones · 7 local ordinances and filings · 246 queue changes- 05 Nov 2026CampusMeta AikenBuilding 2 is operational assuming a 3 month lag compared to Building 1.7601 State Hwy 105, Trenton, SC 29847, USA · Epoch AI, Frontier Data Centers · CC BY 4.0
- 01 Nov 2026CampusOpenAI Stargate AbileneBuildings 7-8 are estimated to be operational. On March 24, Building 8 roughly looked like where Building 3 was in September. Building 3 is estimated to be operational in April, 7 months later. This n…5502 Spinks Rd, Abilene, TX 79601, TX · Epoch AI, Frontier Data Centers · CC BY 4.0
- 31 Oct 2026CampusAnthropic Lake MarinerBuilding 2 (AKA CB4) is operational. On February 26, Terawulf stated that CB4 was expected to be energized by Q3 2026.7725 Lake Rd, Barker, NY 14012, NY · Epoch AI, Frontier Data Centers · CC BY 4.0
- 26 Oct 2026CampusMeta Los LunasBuilding 2 (a tent like building) is operational. Based on a default estimate of 3 months for fit-out after structural completion in July.4250 Messenger Lp, Los Lunas, NM 87031, NM · Epoch AI, Frontier Data Centers · CC BY 4.0
- 23 Oct 2026CampusQTS Cedar RapidsBuildings 1–3 look externally complete, with the air-cooled chillers fully installed, and surrounding yard work cleared. The many cars and trucks parked beside the buildings suggest commissioning is s…6200 76th Ave SW, Fairfax, IA 52228, IA · Epoch AI, Frontier Data Centers · CC BY 4.0
- 19 Oct 2026CampusAnthropic-Amazon New CarlisleBuildings 17-18 are operational. This is an estimate based on a rule of thumb of "operational 5 months after roof is complete", assuming the roofs took one more month after 2025-12-23. Also added four…55001 Larrison Blvd, New Carlisle, IN 46552, IN · Epoch AI, Frontier Data Centers · CC BY 4.0
- 01 Oct 2026MoratoriumNotice of exemptionTulare County, CA · CEQAnet, data center environmental filings · California public record
- 01 Oct 2026MoratoriumNotice of exemptionRiverside County, CA · CEQAnet, data center environmental filings · California public record
- 01 Oct 2026QueueWithdrawn: Black Hawk Solar — Solar, 251.34 MW, DuvalWithdrawnDuval County, TX · ercotqueue.com, monthly queue changes · CC BY 4.0
- 01 Oct 2026QueueWithdrawn: Calico BESS — Battery, 204.9 MW, VictoriaWithdrawnVictoria County, TX · ercotqueue.com, monthly queue changes · CC BY 4.0
- 01 Oct 2026QueueWithdrawn: Running Iron Solar — Solar, 204.74 MW, MatagordaWithdrawnMatagorda County, TX · ercotqueue.com, monthly queue changes · CC BY 4.0
- 01 Oct 2026QueueWithdrawn: Padua Grid BESS Unit 3 — Battery, 201.35 MW, BexarWithdrawnBexar County, TX · ercotqueue.com, monthly queue changes · CC BY 4.0
Alerts for the counties on your shortlist
Alerts for new campuses, queue entries and withdrawals, and local moratoria in the counties or sites you choose. County alerts are set up on request.
Contact us to get accessTalk to us about a region
Bring the counties on your shortlist for a source-by-source review of the evidence.