Matagorda County, TX data center site data
Time to power, land, grid capacity, and risk for Matagorda County, with a source and date for every figure.
Matagorda County time to power and site score
An estimated time-to-power band and a weighted site score summarize the county’s power access, queue readiness, gas access, land, and hazards.
- Readiness
- In study: screening complete, full interconnection study open
Top risks
- Top natural hazards (FEMA NRI): hurricane, drought, heat wave.
- 35%Power access: 99 · max 345 kV substation; 1.0 km to a 115 kV+ line
- 20%Queue readiness: 55 · 54.8% of queued MW has a completed study
- 15%Gas access: 100 · 0.0 km to a gas pipeline
- 15%Land available: 96 · 3.8% protected or public land
- 15%Hazard: 20 · FEMA risk index 80.3
Matagorda County land availability and cost
Large parcels (100 acres or more), open land, land value per acre, protected land, floodplain, soil limits, brownfields, and water access for the county.
Land cover
Share of classified land, from the USDA Cropland Data Layer.
USDA CropScape, land cover by county · Public domainData centers in and near Matagorda County
Operating data centers in the county and within 50 km, with their operators and distance from the county center.
No mapped data centre within 50 km of the county centre.
Mapped facilities are operating sites from the IM3 Atlas. Announced campuses not yet built come from Epoch AI and are not assigned to a county.
Matagorda County natural hazard and permitting risk
FEMA hazard scores and disaster history, air-permitted data centers, local opposition, and ERCOT rule changes that apply to the county.
Hazard scores
FEMA hazard risk scores, shown as national percentiles rather than the probability of loss at a site.
Moratoriums, filings and opposition
No moratorium, ordinance, or opposition news names Matagorda County in the last 30 days. Sources: GDELT news coverage. CEQA filings cover California only.
TX policy changes (statewide)
- 24 Sept 2026Voluntary community-impact RFI option for newly substantiated medium loads
- 21 Sept 2026RIOO RFI visibility restrictions and public question guides
- 14 Sept 2026State and Community Impact RFI issued
- 09 Sept 2026Batch Zero eligibility-verification RFIs issued
- 04 Sept 2026RIOO Off-cycle Release
Matagorda County grid capacity and interconnection queue
Generation queued and operating in the county, transmission and gas access, power prices, and the TX-wide demand that new large loads compete with.
Generation mix
Operating capacity by energy source.
Transmission substations
Substations at the ends of 115 kV and higher lines, from HIFLD.
| Substation | kV | Owner |
|---|---|---|
| Blessing | 345 | — |
| Sotex5 | 345 | — |
| Sotex5 | 345 | AEP TEXAS CENTRAL COMPANY |
| Parish | 345 | CENTERPOINT ENERGY |
| Celanese (Cp) Substation | 138 | AEP TEXAS CENTRAL CO. |
| South Lane City | 138 | AEP TEXAS CENTRAL COMPANY |
| South Lane City | 138 | AEP TEXAS CENTRAL COMPANY |
| Blessing | 138 | AEP TEXAS CENTRAL COMPANY |
| Sotex5 | 138 | — |
| Pledger | 138 | CENTERPOINT ENERGY HOUSTON ELECTRIC, LLC |
Matagorda County construction activity and data center jobs
Data processing and hosting businesses and jobs, and residential building permits as a measure of local construction activity.
Matagorda County queue and demand charts
Queue in county by study stage
Active generation and storage, MW.
This county against the state median
Each figure as a multiple of the TX county median. 1.0 is typical.
Hourly demand profile (TX)
Average TX-wide demand by local hour over the last 14 days, MW.
eia-930-demand-profile · Nov 22, 2026Queued MW in this county by expected online year
Active generation and storage requests, by the year each expects to connect.
ercotqueue.com, interconnection queue projects · CC BY 4.0Sources for every Matagorda County figure
| Figure | Value | As of | Source | License |
|---|---|---|---|---|
| Matagorda County — 300 residential units permitted, 2025 | 300 permits | 01 Jan 2025 | Census Building Permits Survey — county (residential) | US federal work, public domain |
| Matagorda County — $64,299,332 residential permit value, 2025 | 64,299,332 USD | 01 Jan 2025 | Census Building Permits Survey — county (residential) | US federal work, public domain |
| Matagorda — 1 brownfield sites | 1 sites | — | EPA — brownfield sites by county | US federal work, public domain |
| 48321 — cropland 22.15% of classified land (2025) | 22.15 % | 01 Jan 2025 | USDA CropScape — land cover by county | US federal work, public domain |
| 48321 — grassland 43.77% of classified land (2025) | 43.77 % | 01 Jan 2025 | USDA CropScape — land cover by county | US federal work, public domain |
| 48321 — wetlands 16.5% of classified land (2025) | 16.5 % | 01 Jan 2025 | USDA CropScape — land cover by county | US federal work, public domain |
| 48321 — shrubland 1.13% of classified land (2025) | 1.13 % | 01 Jan 2025 | USDA CropScape — land cover by county | US federal work, public domain |
| 48321 — pasture hay 0.45% of classified land (2025) | 0.45 % | 01 Jan 2025 | USDA CropScape — land cover by county | US federal work, public domain |
| 48321 — forest 6.31% of classified land (2025) | 6.31 % | 01 Jan 2025 | USDA CropScape — land cover by county | US federal work, public domain |
| 48321 — developed 4.78% of classified land (2025) | 4.78 % | 01 Jan 2025 | USDA CropScape — land cover by county | US federal work, public domain |
| 48321 — barren 1.22% of classified land (2025) | 1.22 % | 01 Jan 2025 | USDA CropScape — land cover by county | US federal work, public domain |
| 48321 — water 3.69% of classified land (2025) | 3.69 % | 01 Jan 2025 | USDA CropScape — land cover by county | US federal work, public domain |
| 48321 — data-centre employment (2025) — suppressed | suppressed for confidentiality | 01 Jan 2025 | BLS QCEW — data-centre establishments and jobs by county | BLS Quarterly Census of Employment and Wages (US federal work, public domain) |
| 48321 — 2 data-centre establishments (2025) | 2 establishments | 01 Jan 2025 | BLS QCEW — data-centre establishments and jobs by county | BLS Quarterly Census of Employment and Wages (US federal work, public domain) |
| Matagorda County — farmland $3,351 an acre (2022) | 3,351 USD per acre | 01 Jan 2022 | USDA Census of Agriculture — county land value and farm sizes | USDA NASS Census of Agriculture 2022 (US federal work, public domain) |
| Matagorda County — 66.57% in FEMA's 1% annual-chance floodplain | 66.57 % | — | FEMA flood hazard areas — floodplain share | FEMA National Flood Hazard Layer (US federal work, public domain), served by Esri Living Atlas |
| Matagorda County — 652 farms of 100+ acres (2022) | 652 farms | 01 Jan 2022 | USDA Census of Agriculture — county land value and farm sizes | USDA NASS Census of Agriculture 2022 (US federal work, public domain) |
| Matagorda County — 3.79% protected or public land | 3.79 % | — | USGS PAD-US — protected and public land share | US federal work, public domain |
| Matagorda — hydric soils 12.7% | 12.7 % | — | NRCS SSURGO — soil constraints by county | US federal work, public domain |
| Matagorda County — 1.25 km to nearest mapped river | 1.25 km | 01 Nov 2026 | USA Rivers and Streams (distance per county) | Esri Living Atlas, derived from USGS NHD (public domain) |
| Matagorda County — 0.03 km to nearest natural-gas pipeline | 0.03 km | 01 Nov 2026 | EIA — natural gas pipelines (distance per county) | US federal work (EIA), public domain |
| New entry: Ventures BESS — Battery, 238.0 MW, Matagorda | 238 MW | 01 Oct 2026 | ercotqueue.com — monthly queue changes | CC BY 4.0 — ercotqueue.com |
| Withdrawn: Running Iron Solar — Solar, 204.74 MW, Matagorda | 204.74 MW | 01 Oct 2026 | ercotqueue.com — monthly queue changes | CC BY 4.0 — ercotqueue.com |
| Withdrawn: Post Trail Energy — Battery, 103.5 MW, Matagorda | 103.5 MW | 01 Oct 2026 | ercotqueue.com — monthly queue changes | CC BY 4.0 — ercotqueue.com |
| Withdrawn: Razorbill Storage — Battery, 120.0 MW, Matagorda | 120 MW | 01 Sept 2026 | ercotqueue.com — monthly queue changes | CC BY 4.0 — ercotqueue.com |
| Withdrawn: Charolais Storage — Battery, 150.0 MW, Matagorda | 150 MW | 01 Sept 2026 | ercotqueue.com — monthly queue changes | CC BY 4.0 — ercotqueue.com |
| Withdrawn: Charolais Solar — Solar, 261.63 MW, Matagorda | 261.63 MW | 01 Sept 2026 | ercotqueue.com — monthly queue changes | CC BY 4.0 — ercotqueue.com |
| Withdrawn: Razorbill Solar — Solar, 240.0 MW, Matagorda | 240 MW | 01 Sept 2026 | ercotqueue.com — monthly queue changes | CC BY 4.0 — ercotqueue.com |
| Matagorda County — 14 transmission substations (max 345 kV) | 14 substations | 01 Nov 2026 | HIFLD — transmission lines and substations | US federal work (HIFLD), public domain |
| Matagorda County — 0.96 km to nearest 115 kV+ line | 0.96 km | 01 Nov 2026 | HIFLD — transmission lines and substations | US federal work (HIFLD), public domain |
| Wharton County Elec Coop, Inc serves Matagorda County | Wharton County Elec Coop, Inc | 01 Jan 2025 | EIA-861 — utility service territory by county | US federal work, public domain |
| AEP Texas Central Company serves Matagorda County | AEP Texas Central Company | 01 Jan 2025 | EIA-861 — utility service territory by county | US federal work, public domain |
| Jackson Electric Coop, Inc - (TX) serves Matagorda County | Jackson Electric Coop, Inc - (TX) | 01 Jan 2025 | EIA-861 — utility service territory by county | US federal work, public domain |
| Texas-New Mexico Power Co serves Matagorda County | Texas-New Mexico Power Co | 01 Jan 2025 | EIA-861 — utility service territory by county | US federal work, public domain |
| CenterPoint Energy serves Matagorda County | CenterPoint Energy | 01 Jan 2025 | EIA-861 — utility service territory by county | US federal work, public domain |
| Matagorda — expected annual loss $33.3m | 33,307,199 USD | — | FEMA National Risk Index | US federal work (FEMA), public domain |
| Matagorda — NRI risk score 80.3 (Relatively Low) | 80.34 score | — | FEMA National Risk Index | US federal work (FEMA), public domain |
Derived figures — the band, readiness, studied share and comparisons — are CUDO derivations and say so wherever they appear.