Build

Where factories rise.

A data hall aisle under dense overhead cable trays and ducting
Key findings

Frontier AI data centers and construction activity

We’ve mapped 2,271 operating data centers across the states covered so far, and 77 frontier AI campuses in the US account for 12.6 GW of current power. US data center construction spending is up 90% (annualized).
Share of announced pipeline under construction
30–50%of announced pipeline
Hanwha Data Centers · Lawrence Berkeley National Laboratory
Projects facing community opposition
75+projects
· Mar 31, 2026
Operating data centers mapped
2,271facilities
IM3 Data Center Atlas (PNNL) · ODbL 1.0 · Covered states only
US data center construction spending, annualized
$96.5bn
Census C30, data center construction spending · Sep 1, 2026 · Public domain
Data processing and hosting business locations
10,503establishments
Census County Business Patterns, NAICS 518210 · Public domain · Covered counties only. Unit: locations
Rack power density in AI data centers
50–140kW per rack
INTROL
Queue · Sites · Land · News
News and policy

Data center permitting, policy and infrastructure news

Power, policy and construction developments across Texas, California and New York.

60 stories·Latest: Nov 19, 2026
Type
Market
◆ Top storyPolicyUS

Addressing Remote Access to Advanced Semiconductors

In this interim final rule (IFR), the Department of Commerce is establishing new rules to prevent certain foreign actors from leveraging advanced computing power based on U.S. technology to threaten U.S. national security and foreign policy interests. First, this rule establishes new restrictions which will apply for exports, reexports, or transfers (in-country) to overseas data centers that remotely supply significant volumes of compute to companies headquartered in Country Group D:5 or Macau.

US federal (BIS)·Nov 19, 2026
Oct 1, 2026
PolicyCalifornia

Extension of Uncodified Urgency Interim Ordinance No. 3669 - Temporary Moratorium on New Data Center Development

The County of Tulare is extending Uncodified Urgency Interim Ordinance No. 3669, which establishes a temporary moratorium on new data center development in the unincorporated areas of Tulare County. The extension will continue the moratorium for an additional ten (10) months and fifteen (15) days, through August 6, 2027. During the moratorium, the County will continue to evaluate data center development and develop comprehensive land use regulations addressing potential impacts and appropriate d

CEQAnet · Tulare County
Oct 1, 2026
PolicyCalifornia

Extension of Interim Urgency Ordinance No. 2134

The City Council of the City of Palm Springs to adopt an ordinance to extend Interim Urgency Ordinance (Ordinance No. 2134) temporarily prohibiting the approval of applications and permits related to data centers for an additional period of twenty-two (22) months and fifteen (15) days. Interim Urgency Ordinance No. 2134 was adopted by the City Council on August 26, 2026.

CEQAnet · Palm Springs, City of
Sep 24, 2026
PolicyTexas

Voluntary community-impact RFI option for newly substantiated medium loads

ERCOT offered newly substantiated medium-load data-center customers voluntary State and Community Impact RFIs. The request cutoff was October 5, 2026; responses to issued RFIs remain due October 12, 2026 at 5 p.m. CPT. The voluntary option does not alter mandatory RFIs already issued to reported substantiated medium loads.

ERCOT / PUCT
Sep 21, 2026
PolicyTexas

RIOO RFI visibility restrictions and public question guides

ERCOT added RIOO controls restricting respondents' visibility of other submissions and posted question-reference guides for Batch Zero eligibility verification and the separate State and Community Impact RFI. The public guides describe questions, not respondent answers or completed verification.

ERCOT / PUCT
1–5 of 59

Live items come from the pipeline and carry their source. Editorial items are added in the CMS.

Permitting and public sentiment

Data center permitting and public sentiment

Air permits, environmental review, local moratoria, and public sentiment can impact a data center even if it already has a path to power.

Permitting and community signals

Data center records in public permitting registers.

California environmental review filings since 202160
Moratoria or urgency ordinances4
Data centers with air permits15

Of the 15 data centers with a Clean Air Act permit, 12 are in Texas, and all 12 are Title V major sources; 2 are in California, and 1 is in New York.

CEQAnet, data center environmental filings · California public record; EPA ECHO, data center air permits · Nov 23, 2026 · Public domain
Local opposition in the news
Not yet available — needs new ingest

The news feed has not run yet.

California data center environmental review

California’s environmental review law (CEQA) requires public agencies to review discretionary projects, and CEQAnet publishes the filings. These are the latest filings that affect data centers, showing local moratoria and how far individual projects have progressed.

FiledProject or ruleCountyStageWhat it means
01 Oct 2026Extension of Uncodified Urgency Interim Ordinance No. 3669 - Temporary Moratorium on New Data Center DevelopmentTulareMoratoriumA county or city has paused new data center development.
01 Oct 2026Extension of Interim Urgency Ordinance No. 2134RiversideMoratoriumA county or city has paused new data center development.
31 Aug 2026Ordinance imposing a temporary moratorium on Data CentersCalaverasMoratoriumA county or city has paused new data center development.
28 Aug 2026Ordinance No. 821, to Establish an Ordinance adding Chapter 17.42 – Artificial Intelligence (AI) Data Centers & Associated Uses to the Irwindale Municipal Code.Los AngelesExemptExempt from environmental review, typically a small project, rule change, or lease.
19 Aug 2026San Jose Data CenterSanta ClaraApprovedThe local agency has approved the project; it can move on to permits and construction.
05 Aug 2026Vernon Backup Generating FacilityLos AngelesReview startingA full environmental study is about to begin, so the project is at an early stage.
28 Jul 2026Second Amendment to the Riverside County Information Technology Department (RCIT) Chicago Lease Agreement with JS MCA Hunter Park LP, RiversideRiversideExemptExempt from environmental review, typically a small project, rule change, or lease.
21 Jul 2026San Jose Data CenterSanta ClaraApprovedThe local agency has approved the project; it can move on to permits and construction.
21 Jul 2026Northtown Backup Generating FacilitySanta ClaraReview startingA full environmental study is about to begin, so the project is at an early stage.
16 Jul 2026SP25-029 and ER25-243 300 Holger Way Data Center ProjectSanta ClaraExemptExempt from environmental review, typically a small project, rule change, or lease.

Latest 10 of 60 filings since 2021. Each title links to its filing on CEQAnet · California public record

US data center construction spending

Private data center construction put in place each month from 2014 (annualized). Seasonally adjusted annual rate, USD bn.

0 bn24 bn48 bn72 bn96 bn2014-012026-09Census C30, data center construction spending · Public domain
Recent changes

Latest data center construction and permitting changes

Campus milestones, local ordinances, and queue changes from the last 120 days, newest first.

Latest changes

Last 120 days: 26 campus milestones · 7 local ordinances and filings · 246 queue changes
County alerts

Alerts for the counties on your shortlist

Alerts for new campuses, queue entries and withdrawals, and local moratoria in the counties or sites you choose. County alerts are set up on request.

Contact us to get access
Export and share
Related pages

Talk to us about a region

Bring the counties on your shortlist for a source-by-source review of the evidence.

Start a conversation