Ward County, TX data center site data
Time to power, land, grid capacity, and risk for Ward County, with a source and date for every figure.
Ward County time to power and site score
An estimated time-to-power band and a weighted site score summarize the county’s power access, queue readiness, gas access, land, and hazards.
- Readiness
- Interconnection agreement signed
Top risks
- Top natural hazards (FEMA NRI): wildfire, hail, strong wind.
- 35%Power access: 72 · max 138 kV substation; 2.6 km to a 115 kV+ line
- 20%Queue readiness: 72 · 72.1% of queued MW has a completed study
- 15%Gas access: 94 · 2.9 km to a gas pipeline
- 15%Land available: 85 · 15.3% protected or public land
- 15%Hazard: 85 · FEMA risk index 15.4
Ward County grid capacity and interconnection queue
Generation queued and operating in the county, transmission and gas access, power prices, and the TX-wide demand that new large loads compete with.
Generation mix
Operating capacity by energy source.
Transmission substations
Substations at the ends of 115 kV and higher lines, from HIFLD.
| Substation | kV | Owner |
|---|---|---|
| Wickett | 138 | ONCOR ELECTRIC DELIVERY CO. |
| Ward Gulf | 138 | ONCOR ELECTRIC DELIVERY CO. |
| Midway | 138 | ONCOR ELECTRIC DELIVERY CO. |
| Wickett | 138 | ONCOR ELECTRIC DELIVERY CO. |
Ward County land availability and cost
Large parcels (100 acres or more), open land, land value per acre, protected land, floodplain, soil limits, brownfields, and water access for the county.
Land cover
Share of classified land, from the USDA Cropland Data Layer.
USDA CropScape, land cover by county · Public domainData centers in and near Ward County
Operating data centers in the county and within 50 km, with their operators and distance from the county center.
| Facility | Operator | Distance | In county |
|---|---|---|---|
| Data centre | — | 51.2 km | Yes |
| Data centre | — | 51.2 km | Yes |
| IONIC Digital Cedarvale | IONIC Digital | 51.2 km | Yes |
Mapped facilities are operating sites from the IM3 Atlas. Announced campuses not yet built come from Epoch AI and are not assigned to a county.
Ward County natural hazard and permitting risk
FEMA hazard scores and disaster history, air-permitted data centers, local opposition, and ERCOT rule changes that apply to the county.
Hazard scores
FEMA hazard risk scores, shown as national percentiles rather than the probability of loss at a site.
Moratoriums, filings and opposition
No moratorium, ordinance, or opposition news names Ward County in the last 30 days. Sources: GDELT news coverage. CEQA filings cover California only.
TX policy changes (statewide)
- 24 Sept 2026Voluntary community-impact RFI option for newly substantiated medium loads
- 21 Sept 2026RIOO RFI visibility restrictions and public question guides
- 14 Sept 2026State and Community Impact RFI issued
- 09 Sept 2026Batch Zero eligibility-verification RFIs issued
- 04 Sept 2026RIOO Off-cycle Release
Ward County construction activity and data center jobs
Data processing and hosting businesses and jobs, and residential building permits as a measure of local construction activity.
Ward County queue and demand charts
Queue in county by study stage
Active generation and storage, MW.
This county against the state median
Each figure as a multiple of the TX county median. 1.0 is typical.
Hourly demand profile (TX)
Average TX-wide demand by local hour over the last 14 days, MW.
eia-930-demand-profile · Nov 22, 2026Queued MW in this county by expected online year
Active generation and storage requests, by the year each expects to connect.
ercotqueue.com, interconnection queue projects · CC BY 4.0Sources for every Ward County figure
| Figure | Value | As of | Source | License |
|---|---|---|---|---|
| Ward County — 2 mapped data-centre facilities | 2 facilities | — | IM3 Data Center Atlas (PNNL) | ODbL 1.0 (IM3 Open Source Data Center Atlas, PNNL) |
| Ward County — 113,331 sq ft of mapped data-centre footprint | 113,331 sq ft | — | IM3 Data Center Atlas (PNNL) | ODbL 1.0 (IM3 Open Source Data Center Atlas, PNNL) |
| Ward County — 18 residential units permitted, 2025 | 18 permits | 01 Jan 2025 | Census Building Permits Survey — county (residential) | US federal work, public domain |
| Ward County — $910,000 residential permit value, 2025 | 910,000 USD | 01 Jan 2025 | Census Building Permits Survey — county (residential) | US federal work, public domain |
| 48475 — shrubland 91.15% of classified land (2025) | 91.15 % | 01 Jan 2025 | USDA CropScape — land cover by county | US federal work, public domain |
| 48475 — pasture hay 0.01% of classified land (2025) | 0.01 % | 01 Jan 2025 | USDA CropScape — land cover by county | US federal work, public domain |
| 48475 — water 0.12% of classified land (2025) | 0.12 % | 01 Jan 2025 | USDA CropScape — land cover by county | US federal work, public domain |
| 48475 — cropland 0.11% of classified land (2025) | 0.11 % | 01 Jan 2025 | USDA CropScape — land cover by county | US federal work, public domain |
| 48475 — wetlands 0.34% of classified land (2025) | 0.34 % | 01 Jan 2025 | USDA CropScape — land cover by county | US federal work, public domain |
| 48475 — barren 0.94% of classified land (2025) | 0.94 % | 01 Jan 2025 | USDA CropScape — land cover by county | US federal work, public domain |
| 48475 — developed 7.3% of classified land (2025) | 7.3 % | 01 Jan 2025 | USDA CropScape — land cover by county | US federal work, public domain |
| 48475 — grassland 0.02% of classified land (2025) | 0.02 % | 01 Jan 2025 | USDA CropScape — land cover by county | US federal work, public domain |
| 48475 — forest 0.01% of classified land (2025) | 0.01 % | 01 Jan 2025 | USDA CropScape — land cover by county | US federal work, public domain |
| 48475 — data-centre employment (2025): 74 | 74 jobs | 01 Jan 2025 | BLS QCEW — data-centre establishments and jobs by county | BLS Quarterly Census of Employment and Wages (US federal work, public domain) |
| 48475 — 5 data-centre establishments (2025) | 5 establishments | 01 Jan 2025 | BLS QCEW — data-centre establishments and jobs by county | BLS Quarterly Census of Employment and Wages (US federal work, public domain) |
| Ward County — farmland $1,747 an acre (2022) | 1,747 USD per acre | 01 Jan 2022 | USDA Census of Agriculture — county land value and farm sizes | USDA NASS Census of Agriculture 2022 (US federal work, public domain) |
| Ward County — 72 farms of 100+ acres (2022) | 72 farms | 01 Jan 2022 | USDA Census of Agriculture — county land value and farm sizes | USDA NASS Census of Agriculture 2022 (US federal work, public domain) |
| Ward County — 15.28% protected or public land | 15.28 % | — | USGS PAD-US — protected and public land share | US federal work, public domain |
| Ward — no material soil constraint | 0.7 % | — | NRCS SSURGO — soil constraints by county | US federal work, public domain |
| Ward County — 15.89 km to nearest mapped river | 15.89 km | 01 Nov 2026 | USA Rivers and Streams (distance per county) | Esri Living Atlas, derived from USGS NHD (public domain) |
| Ward County — 2.92 km to nearest natural-gas pipeline | 2.92 km | 01 Nov 2026 | EIA — natural gas pipelines (distance per county) | US federal work (EIA), public domain |
| Withdrawn: Frizzle BESS — Battery, 180.9 MW, Ward | 180.9 MW | 01 Oct 2026 | ercotqueue.com — monthly queue changes | CC BY 4.0 — ercotqueue.com |
| Interconnection agreement signed: Vast Sands Power II (TEF-Due Diligence) — Gas, 440.0 MW, Ward | 440 MW | 01 Sept 2026 | ercotqueue.com — monthly queue changes | CC BY 4.0 — ercotqueue.com |
| Interconnection agreement signed: Vast Sands Power I (TEF -Due Diligence) — Gas, 440.0 MW, Ward | 440 MW | 01 Sept 2026 | ercotqueue.com — monthly queue changes | CC BY 4.0 — ercotqueue.com |
| Ward County — 4 transmission substations (max 138 kV) | 4 substations | 01 Nov 2026 | HIFLD — transmission lines and substations | US federal work (HIFLD), public domain |
| Ward County — 2.58 km to nearest 115 kV+ line | 2.58 km | 01 Nov 2026 | HIFLD — transmission lines and substations | US federal work (HIFLD), public domain |
| Texas-New Mexico Power Co serves Ward County | Texas-New Mexico Power Co | 01 Jan 2025 | EIA-861 — utility service territory by county | US federal work, public domain |
| Oncor Electric Delivery Company LLC serves Ward County | Oncor Electric Delivery Company LLC | 01 Jan 2025 | EIA-861 — utility service territory by county | US federal work, public domain |
| Ward — expected annual loss $4.1m | 4,149,288.05 USD | — | FEMA National Risk Index | US federal work (FEMA), public domain |
| Ward — NRI risk score 15.4 (Very Low) | 15.36 score | — | FEMA National Risk Index | US federal work (FEMA), public domain |
Derived figures — the band, readiness, studied share and comparisons — are CUDO derivations and say so wherever they appear.