Ward County, TX data center site data

Time to power, land, grid capacity, and risk for Ward County, with a source and date for every figure.

Site summary

Ward County time to power and site score

An estimated time-to-power band and a weighted site score summarize the county’s power access, queue readiness, gas access, land, and hazards.

Estimated time-to-power band
4–7 yrs
Readiness
Interconnection agreement signed

Top risks

  1. Top natural hazards (FEMA NRI): wildfire, hail, strong wind.
Estimated site score, weighted
79/ 100
  • 35%Power access: 72 · max 138 kV substation; 2.6 km to a 115 kV+ line
  • 20%Queue readiness: 72 · 72.1% of queued MW has a completed study
  • 15%Gas access: 94 · 2.9 km to a gas pipeline
  • 15%Land available: 85 · 15.3% protected or public land
  • 15%Hazard: 85 · FEMA risk index 15.4
Power

Ward County grid capacity and interconnection queue

Generation queued and operating in the county, transmission and gas access, power prices, and the TX-wide demand that new large loads compete with.

Generation and storage queue
3,238MW
Studied share of queue
2,333MW
72.1% of queued MW — derived from ISO status
Large-load queue (ERCOT, state total)
466.5GW
ercotqueue.com, ERCOT large-load funnel · Jun 18, 2026 · CC BY 4.0 · ERCOT publishes large loads for Texas as a whole; no public source names the county
Operating generation
1,195MW
Transmission substations
4substations
HIFLD, transmission lines and substations · Nov 1, 2026 · Public domain · max 138 kV
Distance to 115 kV+ line
2.6km
HIFLD, transmission lines and substations · Nov 1, 2026 · Public domain · from county centre
Distance to gas pipeline
2.9km
EIA, natural gas pipelines (distance per county) · Nov 1, 2026 · Public domain · for on-site generation
Industrial power price
72.1$/MWh
EIA, industrial retail electricity price · Aug 1, 2026 · Public domain · state average
Grid peak and annual demand (ERCOT)
91.1GW
eia-930-demand-profile · Nov 22, 2026 · peak hour, last 12 months · 509 TWh a year · ISO-wide, not this county
TX installed capacity above last year's peak
+96.1%
EIA, operating generator capacity by county · Aug 1, 2026 · Public domain · 178.6 GW installed vs 91.1 GW peak · firm only -4.2%
Queued MW per substation
809MW
ercotqueue.com, interconnection queue projects · CC BY 4.0 · 3,238 MW queued across 4 substations
Utilities serving the county
Oncor Electric Delivery Company LLC · Texas-New Mexico Power Co

Generation mix

Operating capacity by energy source.

Natural GasElectricity used for energy storage

Transmission substations

Substations at the ends of 115 kV and higher lines, from HIFLD.

SubstationkVOwner
Wickett138ONCOR ELECTRIC DELIVERY CO.
Ward Gulf138ONCOR ELECTRIC DELIVERY CO.
Midway138ONCOR ELECTRIC DELIVERY CO.
Wickett138ONCOR ELECTRIC DELIVERY CO.
Land

Ward County land availability and cost

Large parcels (100 acres or more), open land, land value per acre, protected land, floodplain, soil limits, brownfields, and water access for the county.

Farms of 100+ acres
72farms
USDA Census of Agriculture, county land value and farm sizes · Jan 1, 2022 · Public domain · 40 of 1,000+ acres
Open (unbuilt) land
493,258acres
USDA CropScape, land cover by county · Public domain · 92.2% of the county
Farmland value per acre
$1,747per acre
USDA Census of Agriculture, county land value and farm sizes · Jan 1, 2022 · Public domain · agricultural land and buildings, 2022
Protected or public land
15.3%
Flood risk (no digital flood map)
Very Low
inland flooding, FEMA NRI · FEMA National Risk Index · Public domain
Soil constraint
Nonematerial
NRCS SSURGO, soil constraints by county · Public domain · hydric 0.3% · shallow bedrock 0.7%
Brownfield sites
0sites
EPA, brownfield sites by county · Nov 1, 2026 · Public domain · none on the EPA register for this county
Distance to nearest river
15.9km
USA Rivers and Streams (distance per county) · Nov 1, 2026 · to nearest mapped river

Land cover

Share of classified land, from the USDA Cropland Data Layer.

shrubland91.15%
developed7.3%
barren0.94%
wetlands0.34%
water0.12%
cropland0.11%
grassland0.02%
pasture hay0.01%
forest0.01%
USDA CropScape, land cover by county · Public domain
Nearby data centers

Data centers in and near Ward County

Operating data centers in the county and within 50 km, with their operators and distance from the county center.

Mapped data centers in county
3
Data centers within 50 km
3
Straight-line distance from the county center
Mapped footprint
113,331sq ft
Projected future locations (IM3 model)
0locations
IM3, projected data-centre locations · Nov 23, 2026 · ODbL 1.0 · none projected here — IM3 model output, not announcements
FacilityOperatorDistanceIn county
Data centre—51.2 kmYes
Data centre—51.2 kmYes
IONIC Digital CedarvaleIONIC Digital51.2 kmYes

Mapped facilities are operating sites from the IM3 Atlas. Announced campuses not yet built come from Epoch AI and are not assigned to a county.

Risk

Ward County natural hazard and permitting risk

FEMA hazard scores and disaster history, air-permitted data centers, local opposition, and ERCOT rule changes that apply to the county.

FEMA National Risk Index score
15.4score
FEMA National Risk Index · Public domain · Very Low
Expected annual loss
$4.1m
FEMA National Risk Index · Public domain
Disaster declarations since 2010
2
Air-permitted data centres
0facilities
none in this county · epa-echo-datacentre-air

Hazard scores

FEMA hazard risk scores, shown as national percentiles rather than the probability of loss at a site.

wildfire (Relatively Low)75
hail (Relatively Low)70
strong wind (Relatively Moderate)60
drought (Relatively Low)58
winter weather (Relatively Low)58
heat wave (Relatively Low)39

Moratoriums, filings and opposition

No moratorium, ordinance, or opposition news names Ward County in the last 30 days. Sources: GDELT news coverage. CEQA filings cover California only.

TX policy changes (statewide)

  • 24 Sept 2026
    Voluntary community-impact RFI option for newly substantiated medium loads
  • 21 Sept 2026
    RIOO RFI visibility restrictions and public question guides
  • 14 Sept 2026
    State and Community Impact RFI issued
  • 09 Sept 2026
    Batch Zero eligibility-verification RFIs issued
  • 04 Sept 2026
    RIOO Off-cycle Release
Local economy

Ward County construction activity and data center jobs

Data processing and hosting businesses and jobs, and residential building permits as a measure of local construction activity.

Data processing and hosting locations
5establishments
Data processing and hosting jobs
74jobs
Residential units permitted
18permits
Census Building Permits Survey, county (residential) · Jan 1, 2025 · Public domain · Residential only; excludes data centers
Residential permit value
$910,000
County map
Loading map…
Charts

Ward County queue and demand charts

Queue in county by study stage

Active generation and storage, MW.

0 MW558 MW1115 MW1673 MW2230 MWIn studyStudiedIA signed

This county against the state median

Each figure as a multiple of the TX county median. 1.0 is typical.

Generation queue MW2.32×
Studied share2.47×
Transmission substations4×
Km to 115 kV+1.19×
Km to gas pipeline1.03×

Hourly demand profile (TX)

Average TX-wide demand by local hour over the last 14 days, MW.

0 GW13 GW27 GW40 GW54 GW000102030405060708091011121314151617181920212223eia-930-demand-profile · Nov 22, 2026

Queued MW in this county by expected online year

Active generation and storage requests, by the year each expects to connect.

0 MW706 MW1412 MW2118 MW2824 MW2027202820292030ercotqueue.com, interconnection queue projects · CC BY 4.0
Sources

Sources for every Ward County figure

FigureValueAs ofSourceLicense
Ward County — 2 mapped data-centre facilities2 facilities—IM3 Data Center Atlas (PNNL)ODbL 1.0 (IM3 Open Source Data Center Atlas, PNNL)
Ward County — 113,331 sq ft of mapped data-centre footprint113,331 sq ft—IM3 Data Center Atlas (PNNL)ODbL 1.0 (IM3 Open Source Data Center Atlas, PNNL)
Ward County — 18 residential units permitted, 202518 permits01 Jan 2025Census Building Permits Survey — county (residential)US federal work, public domain
Ward County — $910,000 residential permit value, 2025910,000 USD01 Jan 2025Census Building Permits Survey — county (residential)US federal work, public domain
48475 — shrubland 91.15% of classified land (2025)91.15 %01 Jan 2025USDA CropScape — land cover by countyUS federal work, public domain
48475 — pasture hay 0.01% of classified land (2025)0.01 %01 Jan 2025USDA CropScape — land cover by countyUS federal work, public domain
48475 — water 0.12% of classified land (2025)0.12 %01 Jan 2025USDA CropScape — land cover by countyUS federal work, public domain
48475 — cropland 0.11% of classified land (2025)0.11 %01 Jan 2025USDA CropScape — land cover by countyUS federal work, public domain
48475 — wetlands 0.34% of classified land (2025)0.34 %01 Jan 2025USDA CropScape — land cover by countyUS federal work, public domain
48475 — barren 0.94% of classified land (2025)0.94 %01 Jan 2025USDA CropScape — land cover by countyUS federal work, public domain
48475 — developed 7.3% of classified land (2025)7.3 %01 Jan 2025USDA CropScape — land cover by countyUS federal work, public domain
48475 — grassland 0.02% of classified land (2025)0.02 %01 Jan 2025USDA CropScape — land cover by countyUS federal work, public domain
48475 — forest 0.01% of classified land (2025)0.01 %01 Jan 2025USDA CropScape — land cover by countyUS federal work, public domain
48475 — data-centre employment (2025): 7474 jobs01 Jan 2025BLS QCEW — data-centre establishments and jobs by countyBLS Quarterly Census of Employment and Wages (US federal work, public domain)
48475 — 5 data-centre establishments (2025)5 establishments01 Jan 2025BLS QCEW — data-centre establishments and jobs by countyBLS Quarterly Census of Employment and Wages (US federal work, public domain)
Ward County — farmland $1,747 an acre (2022)1,747 USD per acre01 Jan 2022USDA Census of Agriculture — county land value and farm sizesUSDA NASS Census of Agriculture 2022 (US federal work, public domain)
Ward County — 72 farms of 100+ acres (2022)72 farms01 Jan 2022USDA Census of Agriculture — county land value and farm sizesUSDA NASS Census of Agriculture 2022 (US federal work, public domain)
Ward County — 15.28% protected or public land15.28 %—USGS PAD-US — protected and public land shareUS federal work, public domain
Ward — no material soil constraint0.7 %—NRCS SSURGO — soil constraints by countyUS federal work, public domain
Ward County — 15.89 km to nearest mapped river15.89 km01 Nov 2026USA Rivers and Streams (distance per county)Esri Living Atlas, derived from USGS NHD (public domain)
Ward County — 2.92 km to nearest natural-gas pipeline2.92 km01 Nov 2026EIA — natural gas pipelines (distance per county)US federal work (EIA), public domain
Withdrawn: Frizzle BESS — Battery, 180.9 MW, Ward180.9 MW01 Oct 2026ercotqueue.com — monthly queue changesCC BY 4.0 — ercotqueue.com
Interconnection agreement signed: Vast Sands Power II (TEF-Due Diligence) — Gas, 440.0 MW, Ward440 MW01 Sept 2026ercotqueue.com — monthly queue changesCC BY 4.0 — ercotqueue.com
Interconnection agreement signed: Vast Sands Power I (TEF -Due Diligence) — Gas, 440.0 MW, Ward440 MW01 Sept 2026ercotqueue.com — monthly queue changesCC BY 4.0 — ercotqueue.com
Ward County — 4 transmission substations (max 138 kV)4 substations01 Nov 2026HIFLD — transmission lines and substationsUS federal work (HIFLD), public domain
Ward County — 2.58 km to nearest 115 kV+ line2.58 km01 Nov 2026HIFLD — transmission lines and substationsUS federal work (HIFLD), public domain
Texas-New Mexico Power Co serves Ward CountyTexas-New Mexico Power Co01 Jan 2025EIA-861 — utility service territory by countyUS federal work, public domain
Oncor Electric Delivery Company LLC serves Ward CountyOncor Electric Delivery Company LLC01 Jan 2025EIA-861 — utility service territory by countyUS federal work, public domain
Ward — expected annual loss $4.1m4,149,288.05 USD—FEMA National Risk IndexUS federal work (FEMA), public domain
Ward — NRI risk score 15.4 (Very Low)15.36 score—FEMA National Risk IndexUS federal work (FEMA), public domain

Derived figures — the band, readiness, studied share and comparisons — are CUDO derivations and say so wherever they appear.