ConsultationReturn to site
← Power & Energy · County · 48451

Tom Green County, TX data center site data

Time to power, land, grid capacity, and risk for Tom Green County, with a source and date for every figure.

Site summary

Tom Green County time to power and site score

An estimated time-to-power band and a weighted site score summarize the county’s power access, queue readiness, gas access, land, and hazards.

Estimated time-to-power band
2–4 yrs
Readiness
In study: screening complete, full interconnection study open

Top risks

  1. Most queued capacity here is speculative: under a third has a completed study.
  2. Top natural hazards (FEMA NRI): drought, hail, winter weather.
Estimated site score, weighted
66/ 100
  • 35%Power access: 97 · max 345 kV substation; 2.6 km to a 115 kV+ line
  • 20%Queue readiness: 6 · 6.0% of queued MW has a completed study
  • 15%Gas access: 84 · 8.0 km to a gas pipeline
  • 15%Land available: 97 · 2.9% protected or public land
  • 15%Hazard: 23 · FEMA risk index 77.3
Power

Tom Green County grid capacity and interconnection queue

Generation queued and operating in the county, transmission and gas access, power prices, and the TX-wide demand that new large loads compete with.

Generation and storage queue
3,010MW
Studied share of queue
180MW
6% of queued MW — derived from ISO status
Large-load queue (ERCOT, state total)
466.5GW
ercotqueue.com, ERCOT large-load funnel · Jun 18, 2026 · CC BY 4.0 · ERCOT publishes large loads for Texas as a whole; no public source names the county
Operating generation
1,636MW
Transmission substations
8substations
HIFLD, transmission lines and substations · Nov 1, 2026 · Public domain · max 345 kV
Distance to 115 kV+ line
2.6km
HIFLD, transmission lines and substations · Nov 1, 2026 · Public domain · from county centre
Distance to gas pipeline
8km
EIA, natural gas pipelines (distance per county) · Nov 1, 2026 · Public domain · for on-site generation
Industrial power price
72.1$/MWh
EIA, industrial retail electricity price · Aug 1, 2026 · Public domain · state average
Grid peak and annual demand (ERCOT)
91.1GW
eia-930-demand-profile · Nov 22, 2026 · peak hour, last 12 months · 509 TWh a year · ISO-wide, not this county
TX installed capacity above last year's peak
+96.1%
EIA, operating generator capacity by county · Aug 1, 2026 · Public domain · 178.6 GW installed vs 91.1 GW peak · firm only -4.2%
Queued MW per substation
376MW
ercotqueue.com, interconnection queue projects · CC BY 4.0 · 3,010 MW queued across 8 substations
Utilities serving the county
AEP Texas North Company · Coleman County Elec Coop, Inc · Concho Valley Elec Coop Inc · Oncor Electric Delivery Company LLC · Southwest Texas Elec Coop, Inc

Generation mix

Operating capacity by energy source.

SolarWindElectricity used for energy storage

Transmission substations

Substations at the ends of 115 kV and higher lines, from HIFLD.

SubstationkVOwner
San Angelo Red Creek345AEP TEXAS NORTH CO.
San Angelo Red Creek345AEP TEXAS NORTH CO.
Bluff Creek345COLEMAN COUNTY ELEC COOP, INC
Brown345SHARYLAND UTILITIES LP
San Angelo Ben Ficklin138AEP TEXAS NORTH CO.
San Angelo Southland Hills138AEP TEXAS NORTH CO.
San Angelo Ben Ficklin138COLEMAN COUNTY ELEC COOP, INC
San Angelo Red Creek138AEP TEXAS NORTH CO.
Land

Tom Green County land availability and cost

Large parcels (100 acres or more), open land, land value per acre, protected land, floodplain, soil limits, brownfields, and water access for the county.

Farms of 100+ acres
805farms
USDA Census of Agriculture, county land value and farm sizes · Jan 1, 2022 · Public domain · 364 of 1,000+ acres
Open (unbuilt) land
895,037acres
USDA CropScape, land cover by county · Public domain · 90.8% of the county
Farmland value per acre
$2,271per acre
USDA Census of Agriculture, county land value and farm sizes · Jan 1, 2022 · Public domain · agricultural land and buildings, 2022
Protected or public land
2.9%
Floodplain share
11.4%
Soil constraint
32% affected
NRCS SSURGO, soil constraints by county · Public domain · hydric 1.1% · shallow bedrock 31.9%
Brownfield sites
1sites
Distance to nearest river
1.4km
USA Rivers and Streams (distance per county) · Nov 1, 2026 · to nearest mapped river

Land cover

Share of classified land, from the USDA Cropland Data Layer.

shrubland70.95%
cropland19.27%
developed5.48%
forest2.6%
water0.53%
wetlands0.49%
barren0.41%
grassland0.13%
pasture hay0.13%
USDA CropScape, land cover by county · Public domain
Nearby data centers

Data centers in and near Tom Green County

Operating data centers in the county and within 50 km, with their operators and distance from the county center.

Mapped data centers in county
0
Data centers within 50 km
0
Straight-line distance from the county center
Mapped footprint
0sq ft
IM3 Data Center Atlas (PNNL) · Nov 23, 2026 · ODbL 1.0 · no mapped data centre in this county
Projected future locations (IM3 model)
0locations
IM3, projected data-centre locations · Nov 23, 2026 · ODbL 1.0 · none projected here — IM3 model output, not announcements

No mapped data centre within 50 km of the county centre.

Mapped facilities are operating sites from the IM3 Atlas. Announced campuses not yet built come from Epoch AI and are not assigned to a county.

Risk

Tom Green County natural hazard and permitting risk

FEMA hazard scores and disaster history, air-permitted data centers, local opposition, and ERCOT rule changes that apply to the county.

FEMA National Risk Index score
77.3score
FEMA National Risk Index · Public domain · Relatively Low
Expected annual loss
$30.9m
FEMA National Risk Index · Public domain
Disaster declarations since 2010
3
Air-permitted data centres
0facilities
none in this county · epa-echo-datacentre-air

Hazard scores

FEMA hazard risk scores, shown as national percentiles rather than the probability of loss at a site.

drought (Relatively High)97
hail (Relatively High)96
winter weather (Relatively High)95
wildfire (Relatively Moderate)93
heat wave (Relatively Moderate)89
inland flooding (Relatively Moderate)77

Moratoriums, filings and opposition

No moratorium, ordinance, or opposition news names Tom Green County in the last 30 days. Sources: GDELT news coverage. CEQA filings cover California only.

TX policy changes (statewide)

  • 24 Sept 2026
    Voluntary community-impact RFI option for newly substantiated medium loads
  • 21 Sept 2026
    RIOO RFI visibility restrictions and public question guides
  • 14 Sept 2026
    State and Community Impact RFI issued
  • 09 Sept 2026
    Batch Zero eligibility-verification RFIs issued
  • 04 Sept 2026
    RIOO Off-cycle Release
Local economy

Tom Green County construction activity and data center jobs

Data processing and hosting businesses and jobs, and residential building permits as a measure of local construction activity.

Data processing and hosting locations
3establishments
Data processing and hosting jobs
Withheld
BLS QCEW, data-centre establishments and jobs by county · Public domain · BLS suppresses it where a few employers would be identifiable
Residential units permitted
335permits
Census Building Permits Survey, county (residential) · Jan 1, 2025 · Public domain · Residential only; excludes data centers
Residential permit value
$99.4m
County map
Loading map…
Charts

Tom Green County queue and demand charts

Queue in county by study stage

Active generation and storage, MW.

0 MW557 MW1114 MW1670 MW2227 MWIn studyFiledIA signed

This county against the state median

Each figure as a multiple of the TX county median. 1.0 is typical.

Generation queue MW2.16×
Studied share0.21×
Transmission substations8×
Km to 115 kV+1.19×
Km to gas pipeline2.82×

Hourly demand profile (TX)

Average TX-wide demand by local hour over the last 14 days, MW.

0 GW13 GW27 GW40 GW54 GW000102030405060708091011121314151617181920212223eia-930-demand-profile · Nov 22, 2026

Queued MW in this county by expected online year

Active generation and storage requests, by the year each expects to connect.

0 MW447 MW893 MW1340 MW1786 MW202720282029ercotqueue.com, interconnection queue projects · CC BY 4.0
Sources

Sources for every Tom Green County figure

FigureValueAs ofSourceLicense
Tom Green County — 335 residential units permitted, 2025335 permits01 Jan 2025Census Building Permits Survey — county (residential)US federal work, public domain
Tom Green County — $99,430,364 residential permit value, 202599,430,364 USD01 Jan 2025Census Building Permits Survey — county (residential)US federal work, public domain
Tom Green — 1 brownfield sites1 sites—EPA — brownfield sites by countyUS federal work, public domain
48451 — wetlands 0.49% of classified land (2025)0.49 %01 Jan 2025USDA CropScape — land cover by countyUS federal work, public domain
48451 — forest 2.6% of classified land (2025)2.6 %01 Jan 2025USDA CropScape — land cover by countyUS federal work, public domain
48451 — grassland 0.13% of classified land (2025)0.13 %01 Jan 2025USDA CropScape — land cover by countyUS federal work, public domain
48451 — cropland 19.27% of classified land (2025)19.27 %01 Jan 2025USDA CropScape — land cover by countyUS federal work, public domain
48451 — barren 0.41% of classified land (2025)0.41 %01 Jan 2025USDA CropScape — land cover by countyUS federal work, public domain
48451 — developed 5.48% of classified land (2025)5.48 %01 Jan 2025USDA CropScape — land cover by countyUS federal work, public domain
48451 — water 0.53% of classified land (2025)0.53 %01 Jan 2025USDA CropScape — land cover by countyUS federal work, public domain
48451 — pasture hay 0.13% of classified land (2025)0.13 %01 Jan 2025USDA CropScape — land cover by countyUS federal work, public domain
48451 — shrubland 70.95% of classified land (2025)70.95 %01 Jan 2025USDA CropScape — land cover by countyUS federal work, public domain
48451 — data-centre employment (2025) — suppressedsuppressed for confidentiality01 Jan 2025BLS QCEW — data-centre establishments and jobs by countyBLS Quarterly Census of Employment and Wages (US federal work, public domain)
48451 — 3 data-centre establishments (2025)3 establishments01 Jan 2025BLS QCEW — data-centre establishments and jobs by countyBLS Quarterly Census of Employment and Wages (US federal work, public domain)
Tom Green County — farmland $2,271 an acre (2022)2,271 USD per acre01 Jan 2022USDA Census of Agriculture — county land value and farm sizesUSDA NASS Census of Agriculture 2022 (US federal work, public domain)
Tom Green County — 11.39% in FEMA's 1% annual-chance floodplain11.39 %—FEMA flood hazard areas — floodplain shareFEMA National Flood Hazard Layer (US federal work, public domain), served by Esri Living Atlas
Tom Green County — 805 farms of 100+ acres (2022)805 farms01 Jan 2022USDA Census of Agriculture — county land value and farm sizesUSDA NASS Census of Agriculture 2022 (US federal work, public domain)
Tom Green County — 2.94% protected or public land2.94 %—USGS PAD-US — protected and public land shareUS federal work, public domain
Tom Green — shallow bedrock 31.9%31.9 %—NRCS SSURGO — soil constraints by countyUS federal work, public domain
Tom Green County — 1.41 km to nearest mapped river1.41 km01 Nov 2026USA Rivers and Streams (distance per county)Esri Living Atlas, derived from USGS NHD (public domain)
Tom Green County — 8.02 km to nearest natural-gas pipeline8.02 km01 Nov 2026EIA — natural gas pipelines (distance per county)US federal work (EIA), public domain
Tom Green County — 8 transmission substations (max 345 kV)8 substations01 Nov 2026HIFLD — transmission lines and substationsUS federal work (HIFLD), public domain
Tom Green County — 2.59 km to nearest 115 kV+ line2.59 km01 Nov 2026HIFLD — transmission lines and substationsUS federal work (HIFLD), public domain
Southwest Texas Elec Coop, Inc serves Tom Green CountySouthwest Texas Elec Coop, Inc01 Jan 2025EIA-861 — utility service territory by countyUS federal work, public domain
Concho Valley Elec Coop Inc serves Tom Green CountyConcho Valley Elec Coop Inc01 Jan 2025EIA-861 — utility service territory by countyUS federal work, public domain
AEP Texas North Company serves Tom Green CountyAEP Texas North Company01 Jan 2025EIA-861 — utility service territory by countyUS federal work, public domain
Coleman County Elec Coop, Inc serves Tom Green CountyColeman County Elec Coop, Inc01 Jan 2025EIA-861 — utility service territory by countyUS federal work, public domain
Oncor Electric Delivery Company LLC serves Tom Green CountyOncor Electric Delivery Company LLC01 Jan 2025EIA-861 — utility service territory by countyUS federal work, public domain
Tom Green — expected annual loss $30.9m30,903,796.24 USD—FEMA National Risk IndexUS federal work (FEMA), public domain
Tom Green — NRI risk score 77.3 (Relatively Low)77.32 score—FEMA National Risk IndexUS federal work (FEMA), public domain

Derived figures — the band, readiness, studied share and comparisons — are CUDO derivations and say so wherever they appear.

Export and share

Talk to us about Tom Green County

Bring the site and the date. We will walk the evidence with you.