Liberty County, TX data center site data
Time to power, land, grid capacity, and risk for Liberty County, with a source and date for every figure.
Liberty County time to power and site score
An estimated time-to-power band and a weighted site score summarize the county’s power access, queue readiness, gas access, land, and hazards.
- Readiness
- —
Top risks
- Top natural hazards (FEMA NRI): tornado, hurricane, heat wave.
- 35%Power access: 74 · max 138 kV substation; 1.3 km to a 115 kV+ line
- 20%Queue readiness: — · no queue entries
- 15%Gas access: 95 · 2.6 km to a gas pipeline
- 15%Land available: 96 · 3.9% protected or public land
- 15%Hazard: 20 · FEMA risk index 79.5
Liberty County grid capacity and interconnection queue
Generation queued and operating in the county, transmission and gas access, power prices, and the TX-wide demand that new large loads compete with.
Generation mix
Operating capacity by energy source.
Transmission substations
Substations at the ends of 115 kV and higher lines, from HIFLD.
| Substation | kV | Owner |
|---|---|---|
| Jacinto | 138 | ENTERGY TEXAS, INC. |
Liberty County land availability and cost
Large parcels (100 acres or more), open land, land value per acre, protected land, floodplain, soil limits, brownfields, and water access for the county.
Land cover
Share of classified land, from the USDA Cropland Data Layer.
USDA CropScape, land cover by county · Public domainData centers in and near Liberty County
Operating data centers in the county and within 50 km, with their operators and distance from the county center.
No mapped data centre within 50 km of the county centre.
Mapped facilities are operating sites from the IM3 Atlas. Announced campuses not yet built come from Epoch AI and are not assigned to a county.
Liberty County natural hazard and permitting risk
FEMA hazard scores and disaster history, air-permitted data centers, local opposition, and ERCOT rule changes that apply to the county.
Hazard scores
FEMA hazard risk scores, shown as national percentiles rather than the probability of loss at a site.
Moratoriums, filings and opposition
No moratorium, ordinance, or opposition news names Liberty County in the last 30 days. Sources: GDELT news coverage. CEQA filings cover California only.
TX policy changes (statewide)
- 24 Sept 2026Voluntary community-impact RFI option for newly substantiated medium loads
- 21 Sept 2026RIOO RFI visibility restrictions and public question guides
- 14 Sept 2026State and Community Impact RFI issued
- 09 Sept 2026Batch Zero eligibility-verification RFIs issued
- 04 Sept 2026RIOO Off-cycle Release
Liberty County construction activity and data center jobs
Data processing and hosting businesses and jobs, and residential building permits as a measure of local construction activity.
Liberty County queue and demand charts
Queue in county by study stage
Active generation and storage, MW.
No active generation or storage requests in this county.
This county against the state median
Each figure as a multiple of the TX county median. 1.0 is typical.
Hourly demand profile (TX)
Average TX-wide demand by local hour over the last 14 days, MW.
eia-930-demand-profile · Nov 22, 2026Queued MW in this county by expected online year
Active generation and storage requests, by the year each expects to connect.
No dated queue requests in this county.
Sources for every Liberty County figure
| Figure | Value | As of | Source | License |
|---|---|---|---|---|
| Liberty County — 1010 residential units permitted, 2025 | 1,010 permits | 01 Jan 2025 | Census Building Permits Survey — county (residential) | US federal work, public domain |
| Liberty County — $194,371,262 residential permit value, 2025 | 194,371,262 USD | 01 Jan 2025 | Census Building Permits Survey — county (residential) | US federal work, public domain |
| 48291 — forest 16.0% of classified land (2025) | 16 % | 01 Jan 2025 | USDA CropScape — land cover by county | US federal work, public domain |
| 48291 — grassland 30.62% of classified land (2025) | 30.62 % | 01 Jan 2025 | USDA CropScape — land cover by county | US federal work, public domain |
| 48291 — shrubland 2.63% of classified land (2025) | 2.63 % | 01 Jan 2025 | USDA CropScape — land cover by county | US federal work, public domain |
| 48291 — water 1.33% of classified land (2025) | 1.33 % | 01 Jan 2025 | USDA CropScape — land cover by county | US federal work, public domain |
| 48291 — wetlands 33.64% of classified land (2025) | 33.64 % | 01 Jan 2025 | USDA CropScape — land cover by county | US federal work, public domain |
| 48291 — barren 1.09% of classified land (2025) | 1.09 % | 01 Jan 2025 | USDA CropScape — land cover by county | US federal work, public domain |
| 48291 — pasture hay 0.35% of classified land (2025) | 0.35 % | 01 Jan 2025 | USDA CropScape — land cover by county | US federal work, public domain |
| 48291 — cropland 3.5% of classified land (2025) | 3.5 % | 01 Jan 2025 | USDA CropScape — land cover by county | US federal work, public domain |
| 48291 — developed 10.83% of classified land (2025) | 10.83 % | 01 Jan 2025 | USDA CropScape — land cover by county | US federal work, public domain |
| 48291 — data-centre employment (2025): 0 | 0 jobs | 01 Jan 2025 | BLS QCEW — data-centre establishments and jobs by county | BLS Quarterly Census of Employment and Wages (US federal work, public domain) |
| 48291 — 0 data-centre establishments (2025) | 0 establishments | 01 Jan 2025 | BLS QCEW — data-centre establishments and jobs by county | BLS Quarterly Census of Employment and Wages (US federal work, public domain) |
| Liberty County — farmland $4,253 an acre (2022) | 4,253 USD per acre | 01 Jan 2022 | USDA Census of Agriculture — county land value and farm sizes | USDA NASS Census of Agriculture 2022 (US federal work, public domain) |
| Liberty County — 34.55% in FEMA's 1% annual-chance floodplain | 34.55 % | — | FEMA flood hazard areas — floodplain share | FEMA National Flood Hazard Layer (US federal work, public domain), served by Esri Living Atlas |
| Liberty County — 456 farms of 100+ acres (2022) | 456 farms | 01 Jan 2022 | USDA Census of Agriculture — county land value and farm sizes | USDA NASS Census of Agriculture 2022 (US federal work, public domain) |
| Liberty County — 3.89% protected or public land | 3.89 % | — | USGS PAD-US — protected and public land share | US federal work, public domain |
| Liberty — hydric soils 43.7% | 43.7 % | — | NRCS SSURGO — soil constraints by county | US federal work, public domain |
| Liberty County — 6.38 km to nearest mapped river | 6.38 km | 01 Nov 2026 | USA Rivers and Streams (distance per county) | Esri Living Atlas, derived from USGS NHD (public domain) |
| Liberty County — 2.56 km to nearest natural-gas pipeline | 2.56 km | 01 Nov 2026 | EIA — natural gas pipelines (distance per county) | US federal work (EIA), public domain |
| Liberty County — 1 transmission substations (max 138 kV) | 1 substations | 01 Nov 2026 | HIFLD — transmission lines and substations | US federal work (HIFLD), public domain |
| Liberty County — 1.28 km to nearest 115 kV+ line | 1.28 km | 01 Nov 2026 | HIFLD — transmission lines and substations | US federal work (HIFLD), public domain |
| CenterPoint Energy serves Liberty County | CenterPoint Energy | 01 Jan 2025 | EIA-861 — utility service territory by county | US federal work, public domain |
| Entergy Texas Inc. serves Liberty County | Entergy Texas Inc. | 01 Jan 2025 | EIA-861 — utility service territory by county | US federal work, public domain |
| Sam Houston Electric Coop Inc serves Liberty County | Sam Houston Electric Coop Inc | 01 Jan 2025 | EIA-861 — utility service territory by county | US federal work, public domain |
| City of Liberty - (TX) serves Liberty County | City of Liberty - (TX) | 01 Jan 2025 | EIA-861 — utility service territory by county | US federal work, public domain |
| Liberty — expected annual loss $32.5m | 32,533,654.05 USD | — | FEMA National Risk Index | US federal work (FEMA), public domain |
| Liberty — NRI risk score 79.5 (Relatively Low) | 79.52 score | — | FEMA National Risk Index | US federal work (FEMA), public domain |
Derived figures — the band, readiness, studied share and comparisons — are CUDO derivations and say so wherever they appear.
Talk to us about Liberty County
Bring the site and the date. We will walk the evidence with you.
Start a conversation