An estimated time-to-power band and a weighted site score summarize the county’s power access, queue readiness, gas access, land, and hazards.
- Readiness
- In study: screening complete, full interconnection study open
Top risks
- Top natural hazards (FEMA NRI): wildfire, hail, tornado.
- 35%Power access: 49 · max no kV substation; 1.5 km to a 115 kV+ line
- 20%Queue readiness: 38 · 37.7% of queued MW has a completed study
- 15%Gas access: 84 · 8.1 km to a gas pipeline
- 15%Land available: 100 · 0.1% protected or public land
- 15%Hazard: 70 · FEMA risk index 29.9
Lampasas County grid capacity and interconnection queue
Generation queued and operating in the county, transmission and gas access, power prices, and the TX-wide demand that new large loads compete with.
Lampasas County land availability and cost
Large parcels (100 acres or more), open land, land value per acre, protected land, floodplain, soil limits, brownfields, and water access for the county.
Land cover
Share of classified land, from the USDA Cropland Data Layer.
USDA CropScape, land cover by county · Public domainData centers in and near Lampasas County
Operating data centers in the county and within 50 km, with their operators and distance from the county center.
No mapped data centre within 50 km of the county centre.
Mapped facilities are operating sites from the IM3 Atlas. Announced campuses not yet built come from Epoch AI and are not assigned to a county.
Lampasas County natural hazard and permitting risk
FEMA hazard scores and disaster history, air-permitted data centers, local opposition, and ERCOT rule changes that apply to the county.
Hazard scores
FEMA hazard risk scores, shown as national percentiles rather than the probability of loss at a site.
Moratoriums, filings and opposition
No moratorium, ordinance, or opposition news names Lampasas County in the last 30 days. Sources: GDELT news coverage. CEQA filings cover California only.
TX policy changes (statewide)
- 24 Sept 2026Voluntary community-impact RFI option for newly substantiated medium loads
- 21 Sept 2026RIOO RFI visibility restrictions and public question guides
- 14 Sept 2026State and Community Impact RFI issued
- 09 Sept 2026Batch Zero eligibility-verification RFIs issued
- 04 Sept 2026RIOO Off-cycle Release
Lampasas County construction activity and data center jobs
Data processing and hosting businesses and jobs, and residential building permits as a measure of local construction activity.
Lampasas County queue and demand charts
Queue in county by study stage
Active generation and storage, MW.
This county against the state median
Each figure as a multiple of the TX county median. 1.0 is typical.
Hourly demand profile (TX)
Average TX-wide demand by local hour over the last 14 days, MW.
eia-930-demand-profile · Nov 22, 2026Queued MW in this county by expected online year
Active generation and storage requests, by the year each expects to connect.
ercotqueue.com, interconnection queue projects · CC BY 4.0Sources for every Lampasas County figure
| Figure | Value | As of | Source | License |
|---|---|---|---|---|
| Lampasas County — 16 residential units permitted, 2025 | 16 permits | 01 Jan 2025 | Census Building Permits Survey — county (residential) | US federal work, public domain |
| Lampasas County — $4,486,118 residential permit value, 2025 | 4,486,118 USD | 01 Jan 2025 | Census Building Permits Survey — county (residential) | US federal work, public domain |
| 48281 — cropland 1.84% of classified land (2025) | 1.84 % | 01 Jan 2025 | USDA CropScape — land cover by county | US federal work, public domain |
| 48281 — developed 5.59% of classified land (2025) | 5.59 % | 01 Jan 2025 | USDA CropScape — land cover by county | US federal work, public domain |
| 48281 — grassland 3.94% of classified land (2025) | 3.94 % | 01 Jan 2025 | USDA CropScape — land cover by county | US federal work, public domain |
| 48281 — water 0.24% of classified land (2025) | 0.24 % | 01 Jan 2025 | USDA CropScape — land cover by county | US federal work, public domain |
| 48281 — shrubland 69.53% of classified land (2025) | 69.53 % | 01 Jan 2025 | USDA CropScape — land cover by county | US federal work, public domain |
| 48281 — pasture hay 0.46% of classified land (2025) | 0.46 % | 01 Jan 2025 | USDA CropScape — land cover by county | US federal work, public domain |
| 48281 — forest 17.29% of classified land (2025) | 17.29 % | 01 Jan 2025 | USDA CropScape — land cover by county | US federal work, public domain |
| 48281 — barren 0.53% of classified land (2025) | 0.53 % | 01 Jan 2025 | USDA CropScape — land cover by county | US federal work, public domain |
| 48281 — wetlands 0.6% of classified land (2025) | 0.6 % | 01 Jan 2025 | USDA CropScape — land cover by county | US federal work, public domain |
| 48281 — data-centre employment (2025) — suppressed | suppressed for confidentiality | 01 Jan 2025 | BLS QCEW — data-centre establishments and jobs by county | BLS Quarterly Census of Employment and Wages (US federal work, public domain) |
| 48281 — 1 data-centre establishments (2025) | 1 establishments | 01 Jan 2025 | BLS QCEW — data-centre establishments and jobs by county | BLS Quarterly Census of Employment and Wages (US federal work, public domain) |
| Lampasas County — farmland $3,101 an acre (2022) | 3,101 USD per acre | 01 Jan 2022 | USDA Census of Agriculture — county land value and farm sizes | USDA NASS Census of Agriculture 2022 (US federal work, public domain) |
| Lampasas County — 0.01% in FEMA's 1% annual-chance floodplain | 0.01 % | — | FEMA flood hazard areas — floodplain share | FEMA National Flood Hazard Layer (US federal work, public domain), served by Esri Living Atlas |
| Lampasas County — 737 farms of 100+ acres (2022) | 737 farms | 01 Jan 2022 | USDA Census of Agriculture — county land value and farm sizes | USDA NASS Census of Agriculture 2022 (US federal work, public domain) |
| Lampasas County — 0.14% protected or public land | 0.14 % | — | USGS PAD-US — protected and public land share | US federal work, public domain |
| Lampasas — shallow bedrock 72.0% | 72 % | — | NRCS SSURGO — soil constraints by county | US federal work, public domain |
| Lampasas County — 3.24 km to nearest mapped river | 3.24 km | 01 Nov 2026 | USA Rivers and Streams (distance per county) | Esri Living Atlas, derived from USGS NHD (public domain) |
| Lampasas County — 8.07 km to nearest natural-gas pipeline | 8.07 km | 01 Nov 2026 | EIA — natural gas pipelines (distance per county) | US federal work (EIA), public domain |
| Lampasas County — 0 transmission substations | 0 substations | 01 Nov 2026 | HIFLD — transmission lines and substations | US federal work (HIFLD), public domain |
| Lampasas County — 1.47 km to nearest 115 kV+ line | 1.47 km | 01 Nov 2026 | HIFLD — transmission lines and substations | US federal work (HIFLD), public domain |
| Pedernales Electric Coop, Inc serves Lampasas County | Pedernales Electric Coop, Inc | 01 Jan 2025 | EIA-861 — utility service territory by county | US federal work, public domain |
| City of Lampasas - (TX) serves Lampasas County | City of Lampasas - (TX) | 01 Jan 2025 | EIA-861 — utility service territory by county | US federal work, public domain |
| Oncor Electric Delivery Company LLC serves Lampasas County | Oncor Electric Delivery Company LLC | 01 Jan 2025 | EIA-861 — utility service territory by county | US federal work, public domain |
| Hamilton County Elec Coop Assn serves Lampasas County | Hamilton County Elec Coop Assn | 01 Jan 2025 | EIA-861 — utility service territory by county | US federal work, public domain |
| Lampasas — expected annual loss $7.7m | 7,655,678 USD | — | FEMA National Risk Index | US federal work (FEMA), public domain |
| Lampasas — NRI risk score 29.9 (Very Low) | 29.93 score | — | FEMA National Risk Index | US federal work (FEMA), public domain |
Derived figures — the band, readiness, studied share and comparisons — are CUDO derivations and say so wherever they appear.
Talk to us about Lampasas County