ConsultationReturn to site
← Power & Energy · County · 48185

Grimes County, TX data center site data

Time to power, land, grid capacity, and risk for Grimes County, with a source and date for every figure.

Site summary

Grimes County time to power and site score

An estimated time-to-power band and a weighted site score summarize the county’s power access, queue readiness, gas access, land, and hazards.

Estimated time-to-power band
2–4 yrs
Readiness
In study: screening complete, full interconnection study open

Top risks

  1. Top natural hazards (FEMA NRI): drought, hurricane, tornado.
Estimated site score, weighted
78/ 100
  • 35%Power access: 99 · max 345 kV substation; 0.6 km to a 115 kV+ line
  • 20%Queue readiness: 42 · 42.5% of queued MW has a completed study
  • 15%Gas access: 90 · 4.9 km to a gas pipeline
  • 15%Land available: 100 · 0.0% protected or public land
  • 15%Hazard: 43 · FEMA risk index 57.0
Power

Grimes County grid capacity and interconnection queue

Generation queued and operating in the county, transmission and gas access, power prices, and the TX-wide demand that new large loads compete with.

Generation and storage queue
4,438MW
Studied share of queue
1,888MW
42.5% of queued MW — derived from ISO status
Large-load queue (ERCOT, state total)
466.5GW
ercotqueue.com, ERCOT large-load funnel · Jun 18, 2026 · CC BY 4.0 · ERCOT publishes large loads for Texas as a whole; no public source names the county
Operating generation
2,603MW
Transmission substations
7substations
HIFLD, transmission lines and substations · Nov 1, 2026 · Public domain · max 345 kV
Distance to 115 kV+ line
0.6km
HIFLD, transmission lines and substations · Nov 1, 2026 · Public domain · from county centre
Distance to gas pipeline
4.9km
EIA, natural gas pipelines (distance per county) · Nov 1, 2026 · Public domain · for on-site generation
Industrial power price
72.1$/MWh
EIA, industrial retail electricity price · Aug 1, 2026 · Public domain · state average
Grid peak and annual demand (ERCOT)
91.1GW
eia-930-demand-profile · Nov 21, 2026 · peak hour, last 12 months · 509 TWh a year · ISO-wide, not this county
TX installed capacity above last year's peak
+96.1%
EIA, operating generator capacity by county · Aug 1, 2026 · Public domain · 178.6 GW installed vs 91.1 GW peak · firm only -4.2%
Queued MW per substation
634MW
ercotqueue.com, interconnection queue projects · CC BY 4.0 · 4,438 MW queued across 7 substations
Utilities serving the county
Entergy Texas Inc. · Mid-South Electric Coop Assn · San Bernard Electric Coop, Inc

Generation mix

Operating capacity by energy source.

Natural GasSolarElectricity used for energy storage

Transmission substations

Substations at the ends of 115 kV and higher lines, from HIFLD.

SubstationkVOwner
Singleton345MID-SOUTH ELECTRIC COOP ASSN
Singleton345ENTERGY TEXAS INC.
Gibbons Creek345MID-SOUTH ELECTRIC COOP ASSN
Gibbons Creek345MID-SOUTH ELECTRIC COOP ASSN
Twin Oak345ENTERGY TEXAS INC.
Singleton345ENTERGY TEXAS, INC.
Bobville138MID-SOUTH ELECTRIC COOP ASSN
Land

Grimes County land availability and cost

Large parcels (100 acres or more), open land, land value per acre, protected land, floodplain, soil limits, brownfields, and water access for the county.

Farms of 100+ acres
805farms
USDA Census of Agriculture, county land value and farm sizes · Jan 1, 2022 · Public domain · 126 of 1,000+ acres
Open (unbuilt) land
330,987acres
USDA CropScape, land cover by county · Public domain · 64.6% of the county
Farmland value per acre
$3,448per acre
USDA Census of Agriculture, county land value and farm sizes · Jan 1, 2022 · Public domain · agricultural land and buildings, 2022
Protected or public land
0%
Floodplain share
16.7%
Soil constraint
20% affected
NRCS SSURGO, soil constraints by county · Public domain · hydric 3.5% · shallow bedrock 19.6%
Brownfield sites
0sites
EPA, brownfield sites by county · Nov 1, 2026 · Public domain · none on the EPA register for this county
Distance to nearest river
2.3km
USA Rivers and Streams (distance per county) · Nov 1, 2026 · to nearest mapped river

Land cover

Share of classified land, from the USDA Cropland Data Layer.

grassland62.6%
forest20.31%
developed7.05%
wetlands6.44%
water1.33%
shrubland0.82%
cropland0.71%
barren0.42%
pasture hay0.31%
USDA CropScape, land cover by county · Public domain
Nearby data centers

Data centers in and near Grimes County

Operating data centers in the county and within 50 km, with their operators and distance from the county center.

Mapped data centers in county
0
Data centers within 50 km
1
Straight-line distance from the county center
Mapped footprint
0sq ft
IM3 Data Center Atlas (PNNL) · Nov 16, 2026 · ODbL 1.0 · no mapped data centre in this county
Projected future locations (IM3 model)
0locations
IM3, projected data-centre locations · Nov 16, 2026 · ODbL 1.0 · none projected here — IM3 model output, not announcements
FacilityOperatorDistanceIn county
DXC TechnologyDXC Technology48.8 km—

Mapped facilities are operating sites from the IM3 Atlas. Announced campuses not yet built come from Epoch AI and are not assigned to a county.

Risk

Grimes County natural hazard and permitting risk

FEMA hazard scores and disaster history, air-permitted data centers, local opposition, and ERCOT rule changes that apply to the county.

FEMA National Risk Index score
57score
FEMA National Risk Index · Public domain · Relatively Low
Expected annual loss
$14.4m
FEMA National Risk Index · Public domain
Disaster declarations since 2010
5
Air-permitted data centres
0facilities
none in this county · epa-echo-datacentre-air

Hazard scores

FEMA hazard risk scores, shown as national percentiles rather than the probability of loss at a site.

drought (Relatively High)93
hurricane (Relatively Moderate)85
tornado (Relatively Moderate)76
wildfire (Very Low)59
heat wave (Relatively Low)58
strong wind (Relatively Low)38

Moratoriums, filings and opposition

No moratorium, ordinance, or opposition news names Grimes County in the last 30 days. Sources: GDELT news coverage. CEQA filings cover California only.

TX policy changes (statewide)

  • 24 Sept 2026
    Voluntary community-impact RFI option for newly substantiated medium loads
  • 21 Sept 2026
    RIOO RFI visibility restrictions and public question guides
  • 14 Sept 2026
    State and Community Impact RFI issued
  • 09 Sept 2026
    Batch Zero eligibility-verification RFIs issued
  • 04 Sept 2026
    RIOO Off-cycle Release
Local economy

Grimes County construction activity and data center jobs

Data processing and hosting businesses and jobs, and residential building permits as a measure of local construction activity.

Data processing and hosting locations
0establishments
Data processing and hosting jobs
0jobs
Residential units permitted
68permits
Census Building Permits Survey, county (residential) · Jan 1, 2025 · Public domain · Residential only; excludes data centers
Residential permit value
$10.9m
County map
Loading map…
Charts

Grimes County queue and demand charts

Queue in county by study stage

Active generation and storage, MW.

0 MW638 MW1276 MW1913 MW2551 MWIn studyStudiedIA signed

This county against the state median

Each figure as a multiple of the TX county median. 1.0 is typical.

Generation queue MW3.19×
Studied share1.46×
Transmission substations7×
Km to 115 kV+0.28×
Km to gas pipeline1.72×

Hourly demand profile (TX)

Average TX-wide demand by local hour over the last 14 days, MW.

0 GW13 GW27 GW40 GW53 GW000102030405060708091011121314151617181920212223eia-930-demand-profile · Nov 21, 2026

Queued MW in this county by expected online year

Active generation and storage requests, by the year each expects to connect.

0 MW585 MW1170 MW1754 MW2339 MW2026202720282029ercotqueue.com, interconnection queue projects · CC BY 4.0
Sources

Sources for every Grimes County figure

FigureValueAs ofSourceLicense
Grimes County — 68 residential units permitted, 202568 permits01 Jan 2025Census Building Permits Survey — county (residential)US federal work, public domain
Grimes County — $10,868,399 residential permit value, 202510,868,399 USD01 Jan 2025Census Building Permits Survey — county (residential)US federal work, public domain
48185 — forest 20.31% of classified land (2025)20.31 %01 Jan 2025USDA CropScape — land cover by countyUS federal work, public domain
48185 — barren 0.42% of classified land (2025)0.42 %01 Jan 2025USDA CropScape — land cover by countyUS federal work, public domain
48185 — cropland 0.71% of classified land (2025)0.71 %01 Jan 2025USDA CropScape — land cover by countyUS federal work, public domain
48185 — wetlands 6.44% of classified land (2025)6.44 %01 Jan 2025USDA CropScape — land cover by countyUS federal work, public domain
48185 — shrubland 0.82% of classified land (2025)0.82 %01 Jan 2025USDA CropScape — land cover by countyUS federal work, public domain
48185 — pasture hay 0.31% of classified land (2025)0.31 %01 Jan 2025USDA CropScape — land cover by countyUS federal work, public domain
48185 — grassland 62.6% of classified land (2025)62.6 %01 Jan 2025USDA CropScape — land cover by countyUS federal work, public domain
48185 — developed 7.05% of classified land (2025)7.05 %01 Jan 2025USDA CropScape — land cover by countyUS federal work, public domain
48185 — water 1.33% of classified land (2025)1.33 %01 Jan 2025USDA CropScape — land cover by countyUS federal work, public domain
48185 — data-centre employment (2025): 00 jobs01 Jan 2025BLS QCEW — data-centre establishments and jobs by countyBLS Quarterly Census of Employment and Wages (US federal work, public domain)
48185 — 0 data-centre establishments (2025)0 establishments01 Jan 2025BLS QCEW — data-centre establishments and jobs by countyBLS Quarterly Census of Employment and Wages (US federal work, public domain)
Grimes County — farmland $3,448 an acre (2022)3,448 USD per acre01 Jan 2022USDA Census of Agriculture — county land value and farm sizesUSDA NASS Census of Agriculture 2022 (US federal work, public domain)
Grimes County — 16.72% in FEMA's 1% annual-chance floodplain16.72 %—FEMA flood hazard areas — floodplain shareFEMA National Flood Hazard Layer (US federal work, public domain), served by Esri Living Atlas
Grimes County — 805 farms of 100+ acres (2022)805 farms01 Jan 2022USDA Census of Agriculture — county land value and farm sizesUSDA NASS Census of Agriculture 2022 (US federal work, public domain)
Grimes County — 0.01% protected or public land0.01 %—USGS PAD-US — protected and public land shareUS federal work, public domain
Grimes — shallow bedrock 19.6%19.6 %—NRCS SSURGO — soil constraints by countyUS federal work, public domain
Grimes County — 2.27 km to nearest mapped river2.27 km01 Nov 2026USA Rivers and Streams (distance per county)Esri Living Atlas, derived from USGS NHD (public domain)
Grimes County — 4.89 km to nearest natural-gas pipeline4.89 km01 Nov 2026EIA — natural gas pipelines (distance per county)US federal work (EIA), public domain
Withdrawn: Blue Jay Solar — Solar, 141.05 MW, Grimes141.05 MW01 Oct 2026ercotqueue.com — monthly queue changesCC BY 4.0 — ercotqueue.com
Withdrawn: Hill Valley BESS — Battery, 245.8 MW, Grimes245.8 MW01 Oct 2026ercotqueue.com — monthly queue changesCC BY 4.0 — ercotqueue.com
Withdrawn: Blue Jay Solar II — Solar, 68.95 MW, Grimes68.95 MW01 Oct 2026ercotqueue.com — monthly queue changesCC BY 4.0 — ercotqueue.com
Interconnection agreement signed: Eagle Claw Energy Center — Battery, 204.58 MW, Grimes204.58 MW01 Oct 2026ercotqueue.com — monthly queue changesCC BY 4.0 — ercotqueue.com
Withdrawn: Misty Hollow BESS — Battery, 245.8 MW, Grimes245.8 MW01 Oct 2026ercotqueue.com — monthly queue changesCC BY 4.0 — ercotqueue.com
Grimes County — 7 transmission substations (max 345 kV)7 substations01 Nov 2026HIFLD — transmission lines and substationsUS federal work (HIFLD), public domain
Grimes County — 0.6 km to nearest 115 kV+ line0.6 km01 Nov 2026HIFLD — transmission lines and substationsUS federal work (HIFLD), public domain
Mid-South Electric Coop Assn serves Grimes CountyMid-South Electric Coop Assn01 Jan 2025EIA-861 — utility service territory by countyUS federal work, public domain
San Bernard Electric Coop, Inc serves Grimes CountySan Bernard Electric Coop, Inc01 Jan 2025EIA-861 — utility service territory by countyUS federal work, public domain
Entergy Texas Inc. serves Grimes CountyEntergy Texas Inc.01 Jan 2025EIA-861 — utility service territory by countyUS federal work, public domain
Grimes — expected annual loss $14.4m14,408,115.57 USD—FEMA National Risk IndexUS federal work (FEMA), public domain
Grimes — NRI risk score 57.0 (Relatively Low)56.97 score—FEMA National Risk IndexUS federal work (FEMA), public domain

Derived figures — the band, readiness, studied share and comparisons — are CUDO derivations and say so wherever they appear.

Export and share

Talk to us about Grimes County

Bring the site and the date. We will walk the evidence with you.