ConsultationReturn to site
← Power & Energy · County · 48005

Angelina County, TX data center site data

Time to power, land, grid capacity, and risk for Angelina County, with a source and date for every figure.

Site summary

Angelina County time to power and site score

An estimated time-to-power band and a weighted site score summarize the county’s power access, queue readiness, gas access, land, and hazards.

Estimated time-to-power band
2–4 yrs
Readiness
In study: screening complete, full interconnection study open

Top risks

  1. Most queued capacity here is speculative: under a third has a completed study.
  2. Top natural hazards (FEMA NRI): heat wave, strong wind, hurricane.
Estimated site score, weighted
68/ 100
  • 35%Power access: 98 · max 345 kV substation; 2.2 km to a 115 kV+ line
  • 20%Queue readiness: 13 · 13.2% of queued MW has a completed study
  • 15%Gas access: 97 · 1.5 km to a gas pipeline
  • 15%Land available: 82 · 18.1% protected or public land
  • 15%Hazard: 28 · FEMA risk index 71.8
Power

Angelina County grid capacity and interconnection queue

Generation queued and operating in the county, transmission and gas access, power prices, and the TX-wide demand that new large loads compete with.

Generation and storage queue
1,527MW
Studied share of queue
202MW
13.2% of queued MW — derived from ISO status
Large-load queue (ERCOT, state total)
466.5GW
ercotqueue.com, ERCOT large-load funnel · Jun 18, 2026 · CC BY 4.0 · ERCOT publishes large loads for Texas as a whole; no public source names the county
Operating generation
400MW
Transmission substations
1substations
HIFLD, transmission lines and substations · Nov 1, 2026 · Public domain · max 345 kV
Distance to 115 kV+ line
2.2km
HIFLD, transmission lines and substations · Nov 1, 2026 · Public domain · from county centre
Distance to gas pipeline
1.5km
EIA, natural gas pipelines (distance per county) · Nov 1, 2026 · Public domain · for on-site generation
Industrial power price
72.1$/MWh
EIA, industrial retail electricity price · Aug 1, 2026 · Public domain · state average
Grid peak and annual demand (ERCOT)
91.1GW
eia-930-demand-profile · Nov 22, 2026 · peak hour, last 12 months · 509 TWh a year · ISO-wide, not this county
TX installed capacity above last year's peak
+96.1%
EIA, operating generator capacity by county · Aug 1, 2026 · Public domain · 178.6 GW installed vs 91.1 GW peak · firm only -4.2%
Queued MW per substation
1,527MW
ercotqueue.com, interconnection queue projects · CC BY 4.0 · 1,527 MW queued across 1 substations
Utilities serving the county
Houston County Elec Coop Inc · Jasper-Newton Elec Coop, Inc · Oncor Electric Delivery Company LLC · Sam Houston Electric Coop Inc

Generation mix

Operating capacity by energy source.

SolarElectricity used for energy storage

Transmission substations

Substations at the ends of 115 kV and higher lines, from HIFLD.

SubstationkVOwner
Stryker Creek345ONCOR ELECTRIC DELIVERY CO.
Land

Angelina County land availability and cost

Large parcels (100 acres or more), open land, land value per acre, protected land, floodplain, soil limits, brownfields, and water access for the county.

Farms of 100+ acres
330farms
USDA Census of Agriculture, county land value and farm sizes · Jan 1, 2022 · Public domain · 14 of 1,000+ acres
Open (unbuilt) land
132,719acres
USDA CropScape, land cover by county · Public domain · 24% of the county
Farmland value per acre
$4,498per acre
USDA Census of Agriculture, county land value and farm sizes · Jan 1, 2022 · Public domain · agricultural land and buildings, 2022
Protected or public land
18.1%
Floodplain share
28.7%
Soil constraint
10% affected
NRCS SSURGO, soil constraints by county · Public domain · hydric 9.9% · shallow bedrock 10.1%
Brownfield sites
0sites
EPA, brownfield sites by county · Nov 1, 2026 · Public domain · none on the EPA register for this county
Distance to nearest river
3.5km
USA Rivers and Streams (distance per county) · Nov 1, 2026 · to nearest mapped river

Land cover

Share of classified land, from the USDA Cropland Data Layer.

forest43.26%
grassland19.51%
wetlands15.9%
developed10.52%
water6.29%
shrubland3.9%
barren0.57%
pasture hay0.04%
cropland0%
USDA CropScape, land cover by county · Public domain
Nearby data centers

Data centers in and near Angelina County

Operating data centers in the county and within 50 km, with their operators and distance from the county center.

Mapped data centers in county
2
Data centers within 50 km
2
Straight-line distance from the county center
Mapped footprint
12,987sq ft
Projected future locations (IM3 model)
0locations
IM3, projected data-centre locations · Nov 23, 2026 · ODbL 1.0 · none projected here — IM3 model output, not announcements
FacilityOperatorDistanceIn county
Precision Prints Lufkin Datacenter—3.1 kmYes
Data centre—15.3 kmYes

Mapped facilities are operating sites from the IM3 Atlas. Announced campuses not yet built come from Epoch AI and are not assigned to a county.

Risk

Angelina County natural hazard and permitting risk

FEMA hazard scores and disaster history, air-permitted data centers, local opposition, and ERCOT rule changes that apply to the county.

FEMA National Risk Index score
71.8score
FEMA National Risk Index · Public domain · Relatively Low
Expected annual loss
$23.4m
FEMA National Risk Index · Public domain
Disaster declarations since 2010
4
Air-permitted data centres
1facilities
Lufkin Paper Mill (Major Emissions) · EPA ECHO, data center air permits · Public domain

Hazard scores

FEMA hazard risk scores, shown as national percentiles rather than the probability of loss at a site.

heat wave (Relatively Moderate)95
strong wind (Relatively High)93
hurricane (Relatively Low)81
wildfire (Relatively Low)80
winter weather (Relatively Moderate)73
inland flooding (Relatively Low)69

Moratoriums, filings and opposition

No moratorium, ordinance, or opposition news names Angelina County in the last 30 days. Sources: GDELT news coverage. CEQA filings cover California only.

TX policy changes (statewide)

  • 24 Sept 2026
    Voluntary community-impact RFI option for newly substantiated medium loads
  • 21 Sept 2026
    RIOO RFI visibility restrictions and public question guides
  • 14 Sept 2026
    State and Community Impact RFI issued
  • 09 Sept 2026
    Batch Zero eligibility-verification RFIs issued
  • 04 Sept 2026
    RIOO Off-cycle Release
Local economy

Angelina County construction activity and data center jobs

Data processing and hosting businesses and jobs, and residential building permits as a measure of local construction activity.

Data processing and hosting locations
1establishments
Data processing and hosting jobs
Withheld
BLS QCEW, data-centre establishments and jobs by county · Public domain · BLS suppresses it where a few employers would be identifiable
Residential units permitted
157permits
Census Building Permits Survey, county (residential) · Jan 1, 2025 · Public domain · Residential only; excludes data centers
Residential permit value
$40.3m
County map
Loading map…
Charts

Angelina County queue and demand charts

Queue in county by study stage

Active generation and storage, MW.

0 MW332 MW663 MW995 MW1326 MWIn studyStudied

This county against the state median

Each figure as a multiple of the TX county median. 1.0 is typical.

Generation queue MW1.1×
Studied share0.45×
Transmission substations1×
Km to 115 kV+1.03×
Km to gas pipeline0.52×

Hourly demand profile (TX)

Average TX-wide demand by local hour over the last 14 days, MW.

0 GW13 GW27 GW40 GW54 GW000102030405060708091011121314151617181920212223eia-930-demand-profile · Nov 22, 2026

Queued MW in this county by expected online year

Active generation and storage requests, by the year each expects to connect.

0 MW182 MW363 MW545 MW726 MW202820292030ercotqueue.com, interconnection queue projects · CC BY 4.0
Sources

Sources for every Angelina County figure

FigureValueAs ofSourceLicense
Lufkin Paper Mill, LUFKIN — Major Emissions1 facility—EPA ECHO — data center air permitsUS EPA ECHO, public domain
Angelina County — 2 mapped data-centre facilities2 facilities—IM3 Data Center Atlas (PNNL)ODbL 1.0 (IM3 Open Source Data Center Atlas, PNNL)
Angelina County — 12,987 sq ft of mapped data-centre footprint12,987 sq ft—IM3 Data Center Atlas (PNNL)ODbL 1.0 (IM3 Open Source Data Center Atlas, PNNL)
Angelina County — 157 residential units permitted, 2025157 permits01 Jan 2025Census Building Permits Survey — county (residential)US federal work, public domain
Angelina County — $40,337,023 residential permit value, 202540,337,023 USD01 Jan 2025Census Building Permits Survey — county (residential)US federal work, public domain
48005 — shrubland 3.9% of classified land (2025)3.9 %01 Jan 2025USDA CropScape — land cover by countyUS federal work, public domain
48005 — forest 43.26% of classified land (2025)43.26 %01 Jan 2025USDA CropScape — land cover by countyUS federal work, public domain
48005 — cropland 0.0% of classified land (2025)0 %01 Jan 2025USDA CropScape — land cover by countyUS federal work, public domain
48005 — wetlands 15.9% of classified land (2025)15.9 %01 Jan 2025USDA CropScape — land cover by countyUS federal work, public domain
48005 — grassland 19.51% of classified land (2025)19.51 %01 Jan 2025USDA CropScape — land cover by countyUS federal work, public domain
48005 — pasture hay 0.04% of classified land (2025)0.04 %01 Jan 2025USDA CropScape — land cover by countyUS federal work, public domain
48005 — water 6.29% of classified land (2025)6.29 %01 Jan 2025USDA CropScape — land cover by countyUS federal work, public domain
48005 — developed 10.52% of classified land (2025)10.52 %01 Jan 2025USDA CropScape — land cover by countyUS federal work, public domain
48005 — barren 0.57% of classified land (2025)0.57 %01 Jan 2025USDA CropScape — land cover by countyUS federal work, public domain
48005 — data-centre employment (2025) — suppressedsuppressed for confidentiality01 Jan 2025BLS QCEW — data-centre establishments and jobs by countyBLS Quarterly Census of Employment and Wages (US federal work, public domain)
48005 — 1 data-centre establishments (2025)1 establishments01 Jan 2025BLS QCEW — data-centre establishments and jobs by countyBLS Quarterly Census of Employment and Wages (US federal work, public domain)
Angelina County — farmland $4,498 an acre (2022)4,498 USD per acre01 Jan 2022USDA Census of Agriculture — county land value and farm sizesUSDA NASS Census of Agriculture 2022 (US federal work, public domain)
Angelina County — 28.67% in FEMA's 1% annual-chance floodplain28.67 %—FEMA flood hazard areas — floodplain shareFEMA National Flood Hazard Layer (US federal work, public domain), served by Esri Living Atlas
Angelina County — 330 farms of 100+ acres (2022)330 farms01 Jan 2022USDA Census of Agriculture — county land value and farm sizesUSDA NASS Census of Agriculture 2022 (US federal work, public domain)
Angelina County — 18.07% protected or public land18.07 %—USGS PAD-US — protected and public land shareUS federal work, public domain
Angelina — shallow bedrock 10.1%10.1 %—NRCS SSURGO — soil constraints by countyUS federal work, public domain
Angelina County — 3.54 km to nearest mapped river3.54 km01 Nov 2026USA Rivers and Streams (distance per county)Esri Living Atlas, derived from USGS NHD (public domain)
Angelina County — 1.48 km to nearest natural-gas pipeline1.48 km01 Nov 2026EIA — natural gas pipelines (distance per county)US federal work (EIA), public domain
Angelina County — 1 transmission substations (max 345 kV)1 substations01 Nov 2026HIFLD — transmission lines and substationsUS federal work (HIFLD), public domain
Angelina County — 2.23 km to nearest 115 kV+ line2.23 km01 Nov 2026HIFLD — transmission lines and substationsUS federal work (HIFLD), public domain
Houston County Elec Coop Inc serves Angelina CountyHouston County Elec Coop Inc01 Jan 2025EIA-861 — utility service territory by countyUS federal work, public domain
Sam Houston Electric Coop Inc serves Angelina CountySam Houston Electric Coop Inc01 Jan 2025EIA-861 — utility service territory by countyUS federal work, public domain
Jasper-Newton Elec Coop, Inc serves Angelina CountyJasper-Newton Elec Coop, Inc01 Jan 2025EIA-861 — utility service territory by countyUS federal work, public domain
Oncor Electric Delivery Company LLC serves Angelina CountyOncor Electric Delivery Company LLC01 Jan 2025EIA-861 — utility service territory by countyUS federal work, public domain
Angelina — expected annual loss $23.4m23,363,525.06 USD—FEMA National Risk IndexUS federal work (FEMA), public domain
Angelina — NRI risk score 71.8 (Relatively Low)71.82 score—FEMA National Risk IndexUS federal work (FEMA), public domain

Derived figures — the band, readiness, studied share and comparisons — are CUDO derivations and say so wherever they appear.

Export and share

Talk to us about Angelina County

Bring the site and the date. We will walk the evidence with you.

Start a conversation