Fulton County, NY data center site data
Time to power, land, grid capacity, and risk for Fulton County, with a source and date for every figure.
Fulton County time to power and site score
An estimated time-to-power band and a weighted site score summarize the county’s power access, queue readiness, gas access, land, and hazards.
- Readiness
- —
Top risks
- Top natural hazards (FEMA NRI): inland flooding, hurricane, winter weather.
- 35%Power access: 45 · max no kV substation; 4.6 km to a 115 kV+ line
- 20%Queue readiness: — · no queue entries
- 15%Gas access: 51 · 24.4 km to a gas pipeline
- 15%Land available: 72 · 28.2% protected or public land
- 15%Hazard: 51 · FEMA risk index 48.6
Fulton County grid capacity and interconnection queue
Generation queued and operating in the county, transmission and gas access, power prices, and the NY-wide demand that new large loads compete with.
Generation mix
Operating capacity by energy source.
Transmission substations
Substations at the ends of 115 kV and higher lines, from HIFLD.
Fulton County land availability and cost
Large parcels (100 acres or more), open land, land value per acre, protected land, floodplain, soil limits, brownfields, and water access for the county.
Land cover
Share of classified land, from the USDA Cropland Data Layer.
USDA CropScape, land cover by county · Public domainData centers in and near Fulton County
Operating data centers in the county and within 50 km, with their operators and distance from the county center.
No mapped data centre within 50 km of the county centre.
Mapped facilities are operating sites from the IM3 Atlas. Announced campuses not yet built come from Epoch AI and are not assigned to a county.
Fulton County natural hazard and permitting risk
FEMA hazard scores and disaster history, air-permitted data centers, local opposition, and ERCOT rule changes that apply to the county.
Hazard scores
FEMA hazard risk scores, shown as national percentiles rather than the probability of loss at a site.
Moratoriums, filings and opposition
No moratorium, ordinance, or opposition news names Fulton County in the last 30 days. Sources: GDELT news coverage. CEQA filings cover California only.
NY policy changes (statewide)
- 19 Nov 2026
- 14 Jul 2026
- 08 Jul 2026
- 21 Apr 2026
- 15 Jan 2026
Fulton County construction activity and data center jobs
Data processing and hosting businesses and jobs, and residential building permits as a measure of local construction activity.
Fulton County queue and demand charts
Queue in county by study stage
Active generation and storage, MW.
No active generation or storage requests in this county.
This county against the state median
Each figure as a multiple of the NY county median. 1.0 is typical.
Hourly demand profile (NY)
Average NY-wide demand by local hour over the last 15 days, MW.
eia-930-demand-profile · Nov 23, 2026Queued MW in this county by expected online year
Active generation and storage requests, by the year each expects to connect.
No dated queue requests in this county.
Sources for every Fulton County figure
| Figure | Value | As of | Source | License |
|---|---|---|---|---|
| Fulton County — 85 residential units permitted, 2025 | 85 permits | 01 Jan 2025 | Census Building Permits Survey — county (residential) | US federal work, public domain |
| Fulton County — $27,695,915 residential permit value, 2025 | 27,695,915 USD | 01 Jan 2025 | Census Building Permits Survey — county (residential) | US federal work, public domain |
| Fulton — 52 brownfield sites | 52 sites | — | EPA — brownfield sites by county | US federal work, public domain |
| 36035 — forest 65.89% of classified land (2025) | 65.89 % | 01 Jan 2025 | USDA CropScape — land cover by county | US federal work, public domain |
| 36035 — pasture hay 0.81% of classified land (2025) | 0.81 % | 01 Jan 2025 | USDA CropScape — land cover by county | US federal work, public domain |
| 36035 — shrubland 0.42% of classified land (2025) | 0.42 % | 01 Jan 2025 | USDA CropScape — land cover by county | US federal work, public domain |
| 36035 — water 6.79% of classified land (2025) | 6.79 % | 01 Jan 2025 | USDA CropScape — land cover by county | US federal work, public domain |
| 36035 — wetlands 7.94% of classified land (2025) | 7.94 % | 01 Jan 2025 | USDA CropScape — land cover by county | US federal work, public domain |
| 36035 — barren 0.87% of classified land (2025) | 0.87 % | 01 Jan 2025 | USDA CropScape — land cover by county | US federal work, public domain |
| 36035 — grassland 8.12% of classified land (2025) | 8.12 % | 01 Jan 2025 | USDA CropScape — land cover by county | US federal work, public domain |
| 36035 — cropland 1.82% of classified land (2025) | 1.82 % | 01 Jan 2025 | USDA CropScape — land cover by county | US federal work, public domain |
| 36035 — developed 7.34% of classified land (2025) | 7.34 % | 01 Jan 2025 | USDA CropScape — land cover by county | US federal work, public domain |
| 36035 — data-centre employment (2025) — suppressed | suppressed for confidentiality | 01 Jan 2025 | BLS QCEW — data-centre establishments and jobs by county | BLS Quarterly Census of Employment and Wages (US federal work, public domain) |
| 36035 — 2 data-centre establishments (2025) | 2 establishments | 01 Jan 2025 | BLS QCEW — data-centre establishments and jobs by county | BLS Quarterly Census of Employment and Wages (US federal work, public domain) |
| Fulton County — farmland $2,916 an acre (2022) | 2,916 USD per acre | 01 Jan 2022 | USDA Census of Agriculture — county land value and farm sizes | USDA NASS Census of Agriculture 2022 (US federal work, public domain) |
| Fulton County — 0.0% in FEMA's 1% annual-chance floodplain | 0 % | — | FEMA flood hazard areas — floodplain share | FEMA National Flood Hazard Layer (US federal work, public domain), served by Esri Living Atlas |
| Fulton County — 103 farms of 100+ acres (2022) | 103 farms | 01 Jan 2022 | USDA Census of Agriculture — county land value and farm sizes | USDA NASS Census of Agriculture 2022 (US federal work, public domain) |
| Fulton County — 28.18% protected or public land | 28.18 % | — | USGS PAD-US — protected and public land share | US federal work, public domain |
| Fulton — hydric soils 11.2%; shallow bedrock 25.5% | 25.5 % | — | NRCS SSURGO — soil constraints by county | US federal work, public domain |
| Fulton County — 2.07 km to nearest mapped river | 2.07 km | 01 Nov 2026 | USA Rivers and Streams (distance per county) | Esri Living Atlas, derived from USGS NHD (public domain) |
| Fulton County — 24.41 km to nearest natural-gas pipeline | 24.41 km | 01 Nov 2026 | EIA — natural gas pipelines (distance per county) | US federal work (EIA), public domain |
| Fulton County — 0 transmission substations | 0 substations | 01 Nov 2026 | HIFLD — transmission lines and substations | US federal work (HIFLD), public domain |
| Fulton County — 4.58 km to nearest 115 kV+ line | 4.58 km | 01 Nov 2026 | HIFLD — transmission lines and substations | US federal work (HIFLD), public domain |
| Niagara Mohawk Power Corp. serves Fulton County | Niagara Mohawk Power Corp. | 01 Jan 2025 | EIA-861 — utility service territory by county | US federal work, public domain |
| Fulton — expected annual loss $16.5m | 16,540,449.99 USD | — | FEMA National Risk Index | US federal work (FEMA), public domain |
| Fulton — NRI risk score 48.6 (Relatively Low) | 48.63 score | — | FEMA National Risk Index | US federal work (FEMA), public domain |
Derived figures — the band, readiness, studied share and comparisons — are CUDO derivations and say so wherever they appear.
Talk to us about Fulton County
Bring the site and the date. We will walk the evidence with you.