Burnet County time to power and site score

An estimated time-to-power band and a weighted site score summarize the county’s power access, queue readiness, gas access, land, and hazards.

Estimated time-to-power band
4–7 yrs
Readiness
In study: screening complete, full interconnection study open

Top risks

  1. Top natural hazards (FEMA NRI): wildfire, hail, tornado.
Estimated site score, weighted
70/ 100
  • 35%Power access: 72 · max 138 kV substation; 3.3 km to a 115 kV+ line
  • 20%Queue readiness: 62 · 61.6% of queued MW has a completed study
  • 15%Gas access: 96 · 2.1 km to a gas pipeline
  • 15%Land available: 98 · 2.1% protected or public land
  • 15%Hazard: 23 · FEMA risk index 76.6
Land

Burnet County land availability and cost

Large parcels (100 acres or more), open land, land value per acre, protected land, floodplain, soil limits, brownfields, and water access for the county.

Farms of 100+ acres
840farms
USDA Census of Agriculture, county land value and farm sizes · Jan 1, 2022 · Public domain · 134 of 1,000+ acres
Open (unbuilt) land
424,399acres
USDA CropScape, land cover by county · Public domain · 64.9% of the county
Farmland value per acre
$3,738per acre
USDA Census of Agriculture, county land value and farm sizes · Jan 1, 2022 · Public domain · agricultural land and buildings, 2022
Protected or public land
2.1%
Floodplain share
8.3%
Soil constraint
84% affected
NRCS SSURGO, soil constraints by county · Public domain · hydric 0.1% · shallow bedrock 83.8%
Brownfield sites
0sites
EPA, brownfield sites by county · Nov 1, 2026 · Public domain · none on the EPA register for this county
Distance to nearest river
0.1km
USA Rivers and Streams (distance per county) · Nov 1, 2026 · to nearest mapped river

Land cover

Share of classified land, from the USDA Cropland Data Layer.

shrubland58.68%
forest25.73%
developed6.83%
grassland5.13%
water1.93%
barren0.87%
wetlands0.46%
cropland0.27%
pasture hay0.11%
USDA CropScape, land cover by county · Public domain
Nearby data centers

Data centers in and near Burnet County

Operating data centers in the county and within 50 km, with their operators and distance from the county center.

Mapped data centers in county
0
Data centers within 50 km
0
Straight-line distance from the county center
Mapped footprint
0sq ft
IM3 Data Center Atlas (PNNL) · Nov 23, 2026 · ODbL 1.0 · no mapped data centre in this county
Projected future locations (IM3 model)
0locations
IM3, projected data-centre locations · Nov 23, 2026 · ODbL 1.0 · none projected here — IM3 model output, not announcements

No mapped data centre within 50 km of the county centre.

Mapped facilities are operating sites from the IM3 Atlas. Announced campuses not yet built come from Epoch AI and are not assigned to a county.

Risk

Burnet County natural hazard and permitting risk

FEMA hazard scores and disaster history, air-permitted data centers, local opposition, and ERCOT rule changes that apply to the county.

FEMA National Risk Index score
76.6score
FEMA National Risk Index · Public domain · Relatively Low
Expected annual loss
$25.8m
FEMA National Risk Index · Public domain
Disaster declarations since 2010
4
Air-permitted data centres
0facilities
none in this county · epa-echo-datacentre-air

Hazard scores

FEMA hazard risk scores, shown as national percentiles rather than the probability of loss at a site.

wildfire (Relatively Low)89
hail (Relatively Moderate)87
tornado (Relatively Moderate)85
strong wind (Relatively Moderate)83
winter weather (Relatively Moderate)83
inland flooding (Relatively Moderate)82

Moratoriums, filings and opposition

No moratorium, ordinance, or opposition news names Burnet County in the last 30 days. Sources: GDELT news coverage. CEQA filings cover California only.

TX policy changes (statewide)

  • 24 Sept 2026
    Voluntary community-impact RFI option for newly substantiated medium loads
  • 21 Sept 2026
    RIOO RFI visibility restrictions and public question guides
  • 14 Sept 2026
    State and Community Impact RFI issued
  • 09 Sept 2026
    Batch Zero eligibility-verification RFIs issued
  • 04 Sept 2026
    RIOO Off-cycle Release
Power

Burnet County grid capacity and interconnection queue

Generation queued and operating in the county, transmission and gas access, power prices, and the TX-wide demand that new large loads compete with.

Generation and storage queue
271MW
Studied share of queue
167MW
61.6% of queued MW — derived from ISO status
Large-load queue (ERCOT, state total)
466.5GW
ercotqueue.com, ERCOT large-load funnel · Jun 18, 2026 · CC BY 4.0 · ERCOT publishes large loads for Texas as a whole; no public source names the county
Operating generation
217MW
Transmission substations
2substations
HIFLD, transmission lines and substations · Nov 1, 2026 · Public domain · max 138 kV
Distance to 115 kV+ line
3.3km
HIFLD, transmission lines and substations · Nov 1, 2026 · Public domain · from county centre
Distance to gas pipeline
2.1km
EIA, natural gas pipelines (distance per county) · Nov 1, 2026 · Public domain · for on-site generation
Industrial power price
72.1$/MWh
EIA, industrial retail electricity price · Aug 1, 2026 · Public domain · state average
Grid peak and annual demand (ERCOT)
91.1GW
eia-930-demand-profile · Nov 22, 2026 · peak hour, last 12 months · 509 TWh a year · ISO-wide, not this county
TX installed capacity above last year's peak
+96.1%
EIA, operating generator capacity by county · Aug 1, 2026 · Public domain · 178.6 GW installed vs 91.1 GW peak · firm only -4.2%
Queued MW per substation
135MW
ercotqueue.com, interconnection queue projects · CC BY 4.0 · 271 MW queued across 2 substations
Utilities serving the county
City of Burnet - (TX) · Oncor Electric Delivery Company LLC · Pedernales Electric Coop, Inc

Generation mix

Operating capacity by energy source.

Water

Transmission substations

Substations at the ends of 115 kV and higher lines, from HIFLD.

SubstationkVOwner
Lago Vista138ONCOR ELECTRIC DELIVERY CO.
Bee Creek138ONCOR ELECTRIC DELIVERY CO.
Local economy

Burnet County construction activity and data center jobs

Data processing and hosting businesses and jobs, and residential building permits as a measure of local construction activity.

Data processing and hosting locations
2establishments
Data processing and hosting jobs
Withheld
BLS QCEW, data-centre establishments and jobs by county · Public domain · BLS suppresses it where a few employers would be identifiable
Residential units permitted
736permits
Census Building Permits Survey, county (residential) · Jan 1, 2025 · Public domain · Residential only; excludes data centers
Residential permit value
$223.3m
County map
Loading map…
Charts

Burnet County queue and demand charts

Queue in county by study stage

Active generation and storage, MW.

0 MW26 MW52 MW78 MW104 MWStudiedIA signedIn study

This county against the state median

Each figure as a multiple of the TX county median. 1.0 is typical.

Generation queue MW0.19×
Studied share2.11×
Transmission substations2×
Km to 115 kV+1.53×
Km to gas pipeline0.72×

Hourly demand profile (TX)

Average TX-wide demand by local hour over the last 14 days, MW.

0 GW13 GW27 GW40 GW54 GW000102030405060708091011121314151617181920212223eia-930-demand-profile · Nov 22, 2026

Queued MW in this county by expected online year

Active generation and storage requests, by the year each expects to connect.

0 MW42 MW84 MW125 MW167 MW20272028ercotqueue.com, interconnection queue projects · CC BY 4.0
Sources

Sources for every Burnet County figure

FigureValueAs ofSourceLicense
Burnet County — 736 residential units permitted, 2025736 permits01 Jan 2025Census Building Permits Survey — county (residential)US federal work, public domain
Burnet County — $223,312,306 residential permit value, 2025223,312,306 USD01 Jan 2025Census Building Permits Survey — county (residential)US federal work, public domain
48053 — forest 25.73% of classified land (2025)25.73 %01 Jan 2025USDA CropScape — land cover by countyUS federal work, public domain
48053 — pasture hay 0.11% of classified land (2025)0.11 %01 Jan 2025USDA CropScape — land cover by countyUS federal work, public domain
48053 — barren 0.87% of classified land (2025)0.87 %01 Jan 2025USDA CropScape — land cover by countyUS federal work, public domain
48053 — developed 6.83% of classified land (2025)6.83 %01 Jan 2025USDA CropScape — land cover by countyUS federal work, public domain
48053 — grassland 5.13% of classified land (2025)5.13 %01 Jan 2025USDA CropScape — land cover by countyUS federal work, public domain
48053 — water 1.93% of classified land (2025)1.93 %01 Jan 2025USDA CropScape — land cover by countyUS federal work, public domain
48053 — wetlands 0.46% of classified land (2025)0.46 %01 Jan 2025USDA CropScape — land cover by countyUS federal work, public domain
48053 — shrubland 58.68% of classified land (2025)58.68 %01 Jan 2025USDA CropScape — land cover by countyUS federal work, public domain
48053 — cropland 0.27% of classified land (2025)0.27 %01 Jan 2025USDA CropScape — land cover by countyUS federal work, public domain
48053 — data-centre employment (2025) — suppressedsuppressed for confidentiality01 Jan 2025BLS QCEW — data-centre establishments and jobs by countyBLS Quarterly Census of Employment and Wages (US federal work, public domain)
48053 — 2 data-centre establishments (2025)2 establishments01 Jan 2025BLS QCEW — data-centre establishments and jobs by countyBLS Quarterly Census of Employment and Wages (US federal work, public domain)
Burnet County — farmland $3,738 an acre (2022)3,738 USD per acre01 Jan 2022USDA Census of Agriculture — county land value and farm sizesUSDA NASS Census of Agriculture 2022 (US federal work, public domain)
Burnet County — 8.29% in FEMA's 1% annual-chance floodplain8.29 %—FEMA flood hazard areas — floodplain shareFEMA National Flood Hazard Layer (US federal work, public domain), served by Esri Living Atlas
Burnet County — 840 farms of 100+ acres (2022)840 farms01 Jan 2022USDA Census of Agriculture — county land value and farm sizesUSDA NASS Census of Agriculture 2022 (US federal work, public domain)
Burnet County — 2.11% protected or public land2.11 %—USGS PAD-US — protected and public land shareUS federal work, public domain
Burnet — shallow bedrock 83.8%83.8 %—NRCS SSURGO — soil constraints by countyUS federal work, public domain
Burnet County — 0.1 km to nearest mapped river0.1 km01 Nov 2026USA Rivers and Streams (distance per county)Esri Living Atlas, derived from USGS NHD (public domain)
Burnet County — 2.06 km to nearest natural-gas pipeline2.06 km01 Nov 2026EIA — natural gas pipelines (distance per county)US federal work (EIA), public domain
Commissioned: Backbone Creek BESS — Battery, 124.1 MW, Burnet124.1 MW01 Sept 2026ercotqueue.com — monthly queue changesCC BY 4.0 — ercotqueue.com
Burnet County — 2 transmission substations (max 138 kV)2 substations01 Nov 2026HIFLD — transmission lines and substationsUS federal work (HIFLD), public domain
Burnet County — 3.32 km to nearest 115 kV+ line3.32 km01 Nov 2026HIFLD — transmission lines and substationsUS federal work (HIFLD), public domain
Oncor Electric Delivery Company LLC serves Burnet CountyOncor Electric Delivery Company LLC01 Jan 2025EIA-861 — utility service territory by countyUS federal work, public domain
Pedernales Electric Coop, Inc serves Burnet CountyPedernales Electric Coop, Inc01 Jan 2025EIA-861 — utility service territory by countyUS federal work, public domain
City of Burnet - (TX) serves Burnet CountyCity of Burnet - (TX)01 Jan 2025EIA-861 — utility service territory by countyUS federal work, public domain
Burnet — expected annual loss $25.8m25,824,364.11 USD—FEMA National Risk IndexUS federal work (FEMA), public domain
Burnet — NRI risk score 76.6 (Relatively Low)76.62 score—FEMA National Risk IndexUS federal work (FEMA), public domain

Derived figures — the band, readiness, studied share and comparisons — are CUDO derivations and say so wherever they appear.

Export and share

Talk to us about Burnet County

Bring the site and the date. We will walk the evidence with you.

Start a conversation