Site summary

Saratoga County time to power and site score

An estimated time-to-power band and a weighted site score summarize the county’s power access, queue readiness, gas access, land, and hazards.

Estimated time-to-power band
4–7 yrs
Readiness
—

Top risks

  1. Top natural hazards (FEMA NRI): inland flooding, hurricane, earthquake.
Estimated site score, weighted
57/ 100
  • 35%Power access: 61 · max 115 kV substation; 4.4 km to a 115 kV+ line
  • 20%Queue readiness: — · no queue entries
  • 15%Gas access: 45 · 27.6 km to a gas pipeline
  • 15%Land available: 91 · 8.8% protected or public land
  • 15%Hazard: 27 · FEMA risk index 73.0
Land

Saratoga County land availability and cost

Large parcels (100 acres or more), open land, land value per acre, protected land, floodplain, soil limits, brownfields, and water access for the county.

Farms of 100+ acres
241farms
USDA Census of Agriculture, county land value and farm sizes · Jan 1, 2022 · Public domain · 22 of 1,000+ acres
Open (unbuilt) land
81,435acres
USDA CropScape, land cover by county · Public domain · 15.1% of the county
Farmland value per acre
$6,689per acre
USDA Census of Agriculture, county land value and farm sizes · Jan 1, 2022 · Public domain · agricultural land and buildings, 2022
Protected or public land
8.8%
Floodplain share
0.3%
Soil constraint
21% affected
NRCS SSURGO, soil constraints by county · Public domain · hydric 9% · shallow bedrock 20.7%
Brownfield sites
2sites
Distance to nearest river
2.5km
USA Rivers and Streams (distance per county) · Nov 1, 2026 · to nearest mapped river

Land cover

Share of classified land, from the USDA Cropland Data Layer.

forest54.43%
developed17.16%
wetlands9.1%
grassland8.24%
cropland4.07%
water3.72%
shrubland1.7%
barren1.07%
pasture hay0.5%
USDA CropScape, land cover by county · Public domain
Nearby data centers

Data centers in and near Saratoga County

Operating data centers in the county and within 50 km, with their operators and distance from the county center.

Mapped data centers in county
0
Data centers within 50 km
4
Straight-line distance from the county center
Mapped footprint
0sq ft
IM3 Data Center Atlas (PNNL) · Nov 23, 2026 · ODbL 1.0 · no mapped data centre in this county
Projected future locations (IM3 model)
0locations
IM3, projected data-centre locations · Nov 23, 2026 · ODbL 1.0 · none projected here — IM3 model output, not announcements
FacilityOperatorDistanceIn county
Turnkey Internet—29.3 km—
Lumen Albany 4Lumen Technologies30.4 km—
Data centre—40 km—
IBM Building—40 km—

Mapped facilities are operating sites from the IM3 Atlas. Announced campuses not yet built come from Epoch AI and are not assigned to a county.

Risk

Saratoga County natural hazard and permitting risk

FEMA hazard scores and disaster history, air-permitted data centers, local opposition, and ERCOT rule changes that apply to the county.

FEMA National Risk Index score
73score
FEMA National Risk Index · Public domain · Relatively Low
Expected annual loss
$53m
FEMA National Risk Index · Public domain
Disaster declarations since 2010
6
Air-permitted data centres
0facilities
none in this county · epa-echo-datacentre-air

Hazard scores

FEMA hazard risk scores, shown as national percentiles rather than the probability of loss at a site.

inland flooding (Relatively Moderate)83
hurricane (Relatively Low)78
earthquake (Relatively Low)73
tornado (Relatively Moderate)70
strong wind (Relatively Moderate)63
heat wave (Relatively Low)59
Power

Saratoga County grid capacity and interconnection queue

Generation queued and operating in the county, transmission and gas access, power prices, and the NY-wide demand that new large loads compete with.

Generation and storage queue
—
No active entries
Studied share of queue
—
No queue entries
Large-load queue
40MW
Operating generation
1,163MW
Transmission substations
19substations
HIFLD, transmission lines and substations · Nov 1, 2026 · Public domain · max 115 kV
Distance to 115 kV+ line
4.4km
HIFLD, transmission lines and substations · Nov 1, 2026 · Public domain · from county centre
Distance to gas pipeline
27.7km
EIA, natural gas pipelines (distance per county) · Nov 1, 2026 · Public domain · for on-site generation
Industrial power price
105.4$/MWh
EIA, industrial retail electricity price · Aug 1, 2026 · Public domain · state average
Grid peak and annual demand (NYISO)
31.1GW
eia-930-demand-profile · Nov 23, 2026 · peak hour, last 12 months · 151 TWh a year · ISO-wide, not this county
NY installed capacity above last year's peak
+38.4%
EIA, operating generator capacity by county · Aug 1, 2026 · Public domain · 43 GW installed vs 31.1 GW peak · firm only +18.3%
Queued MW per substation
0MW
HIFLD, transmission lines and substations · Public domain · no active queue requests in this county
Utilities serving the county
New York State Elec & Gas Corp · Niagara Mohawk Power Corp.

Generation mix

Operating capacity by energy source.

WaterNatural GasSolarElectricity used for energy storage

Transmission substations

Substations at the ends of 115 kV and higher lines, from HIFLD.

SubstationkVOwner
Mohican115NIAGARA MOHAWK POWER CORP.
E J West115NIAGARA MOHAWK POWER CORP.
Kce Ny 1115—
Brookfield Power Glen Falls Hydro115NIAGARA MOHAWK POWER CORP.
Sodeman115NIAGARA MOHAWK POWER CORP.
Butler115NIAGARA MOHAWK POWER CORP.
Ballston115NIAGARA MOHAWK POWER CORP.
Lasher115NIAGARA MOHAWK POWER CORP.
Butler115NIAGARA MOHAWK POWER CORP.
Mohican115NIAGARA MOHAWK POWER CORP.
Local economy

Saratoga County construction activity and data center jobs

Data processing and hosting businesses and jobs, and residential building permits as a measure of local construction activity.

Data processing and hosting locations
20establishments
Data processing and hosting jobs
195jobs
Residential units permitted
884permits
Census Building Permits Survey, county (residential) · Jan 1, 2025 · Public domain · Residential only; excludes data centers
Residential permit value
$348.8m
County map
Loading map…
Charts

Saratoga County queue and demand charts

Queue in county by study stage

Active generation and storage, MW.

No active generation or storage requests in this county.

This county against the state median

Each figure as a multiple of the NY county median. 1.0 is typical.

Transmission substations2.71×
Km to 115 kV+2.13×
Km to gas pipeline3.66×

Hourly demand profile (NY)

Average NY-wide demand by local hour over the last 15 days, MW.

0 GW5 GW9 GW14 GW18 GW000102030405060708091011121314151617181920212223eia-930-demand-profile · Nov 23, 2026

Queued MW in this county by expected online year

Active generation and storage requests, by the year each expects to connect.

No dated queue requests in this county.

Sources

Sources for every Saratoga County figure

FigureValueAs ofSourceLicense
Saratoga County — 884 residential units permitted, 2025884 permits01 Jan 2025Census Building Permits Survey — county (residential)US federal work, public domain
Saratoga County — $348,755,155 residential permit value, 2025348,755,155 USD01 Jan 2025Census Building Permits Survey — county (residential)US federal work, public domain
Saratoga — 2 brownfield sites2 sites—EPA — brownfield sites by countyUS federal work, public domain
36091 — barren 1.07% of classified land (2025)1.07 %01 Jan 2025USDA CropScape — land cover by countyUS federal work, public domain
36091 — shrubland 1.7% of classified land (2025)1.7 %01 Jan 2025USDA CropScape — land cover by countyUS federal work, public domain
36091 — wetlands 9.1% of classified land (2025)9.1 %01 Jan 2025USDA CropScape — land cover by countyUS federal work, public domain
36091 — water 3.72% of classified land (2025)3.72 %01 Jan 2025USDA CropScape — land cover by countyUS federal work, public domain
36091 — pasture hay 0.5% of classified land (2025)0.5 %01 Jan 2025USDA CropScape — land cover by countyUS federal work, public domain
36091 — developed 17.16% of classified land (2025)17.16 %01 Jan 2025USDA CropScape — land cover by countyUS federal work, public domain
36091 — grassland 8.24% of classified land (2025)8.24 %01 Jan 2025USDA CropScape — land cover by countyUS federal work, public domain
36091 — forest 54.43% of classified land (2025)54.43 %01 Jan 2025USDA CropScape — land cover by countyUS federal work, public domain
36091 — cropland 4.07% of classified land (2025)4.07 %01 Jan 2025USDA CropScape — land cover by countyUS federal work, public domain
36091 — data-centre employment (2025): 195195 jobs01 Jan 2025BLS QCEW — data-centre establishments and jobs by countyBLS Quarterly Census of Employment and Wages (US federal work, public domain)
36091 — 20 data-centre establishments (2025)20 establishments01 Jan 2025BLS QCEW — data-centre establishments and jobs by countyBLS Quarterly Census of Employment and Wages (US federal work, public domain)
Saratoga County — farmland $6,689 an acre (2022)6,689 USD per acre01 Jan 2022USDA Census of Agriculture — county land value and farm sizesUSDA NASS Census of Agriculture 2022 (US federal work, public domain)
Saratoga County — 0.25% in FEMA's 1% annual-chance floodplain0.25 %—FEMA flood hazard areas — floodplain shareFEMA National Flood Hazard Layer (US federal work, public domain), served by Esri Living Atlas
Saratoga County — 241 farms of 100+ acres (2022)241 farms01 Jan 2022USDA Census of Agriculture — county land value and farm sizesUSDA NASS Census of Agriculture 2022 (US federal work, public domain)
Saratoga County — 8.75% protected or public land8.75 %—USGS PAD-US — protected and public land shareUS federal work, public domain
Saratoga — shallow bedrock 20.7%20.7 %—NRCS SSURGO — soil constraints by countyUS federal work, public domain
Saratoga County — 2.47 km to nearest mapped river2.47 km01 Nov 2026USA Rivers and Streams (distance per county)Esri Living Atlas, derived from USGS NHD (public domain)
Saratoga Expansion — Consumable goods manufacturing (40 MW)40 MW31 Aug 2026NYISO interconnection queue, including large loadsNYISO public interconnection queue — attribute NYISO
Saratoga County — 27.65 km to nearest natural-gas pipeline27.65 km01 Nov 2026EIA — natural gas pipelines (distance per county)US federal work (EIA), public domain
Saratoga County — 19 transmission substations (max 115 kV)19 substations01 Nov 2026HIFLD — transmission lines and substationsUS federal work (HIFLD), public domain
Saratoga County — 4.43 km to nearest 115 kV+ line4.43 km01 Nov 2026HIFLD — transmission lines and substationsUS federal work (HIFLD), public domain
New York State Elec & Gas Corp serves Saratoga CountyNew York State Elec & Gas Corp01 Jan 2025EIA-861 — utility service territory by countyUS federal work, public domain
Niagara Mohawk Power Corp. serves Saratoga CountyNiagara Mohawk Power Corp.01 Jan 2025EIA-861 — utility service territory by countyUS federal work, public domain
Saratoga — expected annual loss $53.0m52,968,209.09 USD—FEMA National Risk IndexUS federal work (FEMA), public domain
Saratoga — NRI risk score 73.0 (Relatively Low)73.03 score—FEMA National Risk IndexUS federal work (FEMA), public domain

Derived figures — the band, readiness, studied share and comparisons — are CUDO derivations and say so wherever they appear.

Export and share

Talk to us about Saratoga County

Bring the site and the date. We will walk the evidence with you.