Niagara County, NY data center site data
Time to power, land, grid capacity, and risk for Niagara County, with a source and date for every figure.
Niagara County time to power and site score
An estimated time-to-power band and a weighted site score summarize the county’s power access, queue readiness, gas access, land, and hazards.
- Readiness
- Studied, not yet agreed
Top risks
- Top natural hazards (FEMA NRI): inland flooding, strong wind, earthquake.
- 35%Power access: 99 · max 345 kV substation; 0.6 km to a 115 kV+ line
- 20%Queue readiness: 100 · 100.0% of queued MW has a completed study
- 15%Gas access: 95 · 2.5 km to a gas pipeline
- 15%Land available: 98 · 2.0% protected or public land
- 15%Hazard: 17 · FEMA risk index 83.4
Niagara County land availability and cost
Large parcels (100 acres or more), open land, land value per acre, protected land, floodplain, soil limits, brownfields, and water access for the county.
Land cover
Share of classified land, from the USDA Cropland Data Layer.
USDA CropScape, land cover by county · Public domainData centers in and near Niagara County
Operating data centers in the county and within 50 km, with their operators and distance from the county center.
| Facility | Operator | Distance | In county |
|---|---|---|---|
| Blockfusion | Blockfusion | 10.1 km | Yes |
| Data centre | — | 12.9 km | — |
| Blockfusion Niagra Falls | — | 13.6 km | Yes |
| Blockfusion Niagra Falls | — | 13.6 km | Yes |
| Blockfusion Niagra Falls | — | 13.6 km | Yes |
| Blockfusion Niagra Falls | — | 13.6 km | Yes |
| Blockfusion Niagra Falls | — | 13.6 km | Yes |
| Blockfusion Niagra Falls | — | 13.6 km | Yes |
| Blockfusion Niagra Falls | — | 13.6 km | Yes |
| Blockfusion Niagra Falls | — | 13.6 km | Yes |
| Blockfusion Niagra Falls | — | 13.7 km | Yes |
| Blockfusion Niagra Falls | — | 13.7 km | Yes |
| Blockfusion Niagra Falls | — | 13.7 km | Yes |
| US Bitcoin | US Bitcoin | 15.7 km | Yes |
| Frontier Science | — | 16.3 km | — |
Mapped facilities are operating sites from the IM3 Atlas. Announced campuses not yet built come from Epoch AI and are not assigned to a county.
Niagara County natural hazard and permitting risk
FEMA hazard scores and disaster history, air-permitted data centers, local opposition, and ERCOT rule changes that apply to the county.
Hazard scores
FEMA hazard risk scores, shown as national percentiles rather than the probability of loss at a site.
Moratoriums, filings and opposition
No moratorium, ordinance, or opposition news names Niagara County in the last 30 days. Sources: GDELT news coverage. CEQA filings cover California only.
NY policy changes (statewide)
- 19 Nov 2026
- 14 Jul 2026
- 08 Jul 2026
- 21 Apr 2026
- 15 Jan 2026
Niagara County grid capacity and interconnection queue
Generation queued and operating in the county, transmission and gas access, power prices, and the NY-wide demand that new large loads compete with.
Generation mix
Operating capacity by energy source.
Transmission substations
Substations at the ends of 115 kV and higher lines, from HIFLD.
| Substation | kV | Owner |
|---|---|---|
| Somerset | 345 | NIAGARA MOHAWK POWER CORP. |
| Rochester #80 | 345 | — |
| Niagara | 345 | NIAGARA MOHAWK POWER CORP. |
| Rochester #80 | 345 | ROCHESTER GAS & ELECTRIC CORP |
| Somerset Operating Co Llc | 345 | — |
| Niagara | 345 | NIAGARA MOHAWK POWER CORP. |
| Packard | 230 | NIAGARA MOHAWK POWER CORP. |
| Stolle Road | 230 | NEW YORK STATE ELEC & GAS CORP |
| Robinson Road | 230 | NEW YORK STATE ELEC & GAS CORP |
| Indian Hill Switch | 115 | NIAGARA MOHAWK POWER CORP. |
Niagara County construction activity and data center jobs
Data processing and hosting businesses and jobs, and residential building permits as a measure of local construction activity.
Niagara County queue and demand charts
Queue in county by study stage
Active generation and storage, MW.
This county against the state median
Each figure as a multiple of the NY county median. 1.0 is typical.
Hourly demand profile (NY)
Average NY-wide demand by local hour over the last 15 days, MW.
eia-930-demand-profile · Nov 23, 2026Queued MW in this county by expected online year
Active generation and storage requests, by the year each expects to connect.
NYISO interconnection queue, including large loadsSources for every Niagara County figure
| Figure | Value | As of | Source | License |
|---|---|---|---|---|
| Core42 Lake Mariner — 58 MW (Core42 #confident) | 58 MW | — | Epoch AI — Frontier Data Centers | CC BY 4.0 (Epoch AI, ‘AI data centers’) |
| Anthropic Lake Mariner — 210 MW (AI XPV Platform #confident) | 210 MW | — | Epoch AI — Frontier Data Centers | CC BY 4.0 (Epoch AI, ‘AI data centers’) |
| Niagara County — 13 mapped data-centre facilities | 13 facilities | — | IM3 Data Center Atlas (PNNL) | ODbL 1.0 (IM3 Open Source Data Center Atlas, PNNL) |
| Niagara County — 117,171 sq ft of mapped data-centre footprint | 117,171 sq ft | — | IM3 Data Center Atlas (PNNL) | ODbL 1.0 (IM3 Open Source Data Center Atlas, PNNL) |
| Niagara County — 271 residential units permitted, 2025 | 271 permits | 01 Jan 2025 | Census Building Permits Survey — county (residential) | US federal work, public domain |
| Niagara County — $102,943,490 residential permit value, 2025 | 102,943,490 USD | 01 Jan 2025 | Census Building Permits Survey — county (residential) | US federal work, public domain |
| Core42 Lake Mariner — $2.2bn total capital cost (2025 USD) | 2,197,156,000 USD | — | Epoch AI — Frontier Data Centers | CC BY 4.0 (Epoch AI, ‘AI data centers’) |
| Anthropic Lake Mariner — $8.0bn total capital cost (2025 USD) | 7,955,220,000 USD | — | Epoch AI — Frontier Data Centers | CC BY 4.0 (Epoch AI, ‘AI data centers’) |
| Niagara — 186 brownfield sites | 186 sites | — | EPA — brownfield sites by county | US federal work, public domain |
| 36063 — wetlands 13.71% of classified land (2025) | 13.71 % | 01 Jan 2025 | USDA CropScape — land cover by county | US federal work, public domain |
| 36063 — shrubland 0.94% of classified land (2025) | 0.94 % | 01 Jan 2025 | USDA CropScape — land cover by county | US federal work, public domain |
| 36063 — grassland 20.14% of classified land (2025) | 20.14 % | 01 Jan 2025 | USDA CropScape — land cover by county | US federal work, public domain |
| 36063 — developed 20.61% of classified land (2025) | 20.61 % | 01 Jan 2025 | USDA CropScape — land cover by county | US federal work, public domain |
| 36063 — barren 1.06% of classified land (2025) | 1.06 % | 01 Jan 2025 | USDA CropScape — land cover by county | US federal work, public domain |
| 36063 — water 1.13% of classified land (2025) | 1.13 % | 01 Jan 2025 | USDA CropScape — land cover by county | US federal work, public domain |
| 36063 — forest 13.3% of classified land (2025) | 13.3 % | 01 Jan 2025 | USDA CropScape — land cover by county | US federal work, public domain |
| 36063 — pasture hay 3.23% of classified land (2025) | 3.23 % | 01 Jan 2025 | USDA CropScape — land cover by county | US federal work, public domain |
| 36063 — cropland 25.88% of classified land (2025) | 25.88 % | 01 Jan 2025 | USDA CropScape — land cover by county | US federal work, public domain |
| 36063 — data-centre employment (2025) — suppressed | suppressed for confidentiality | 01 Jan 2025 | BLS QCEW — data-centre establishments and jobs by county | BLS Quarterly Census of Employment and Wages (US federal work, public domain) |
| 36063 — 4 data-centre establishments (2025) | 4 establishments | 01 Jan 2025 | BLS QCEW — data-centre establishments and jobs by county | BLS Quarterly Census of Employment and Wages (US federal work, public domain) |
| Niagara County — farmland $3,796 an acre (2022) | 3,796 USD per acre | 01 Jan 2022 | USDA Census of Agriculture — county land value and farm sizes | USDA NASS Census of Agriculture 2022 (US federal work, public domain) |
| Niagara County — 9.29% in FEMA's 1% annual-chance floodplain | 9.29 % | — | FEMA flood hazard areas — floodplain share | FEMA National Flood Hazard Layer (US federal work, public domain), served by Esri Living Atlas |
| Niagara County — 232 farms of 100+ acres (2022) | 232 farms | 01 Jan 2022 | USDA Census of Agriculture — county land value and farm sizes | USDA NASS Census of Agriculture 2022 (US federal work, public domain) |
| Niagara County — 1.97% protected or public land | 1.97 % | — | USGS PAD-US — protected and public land share | US federal work, public domain |
| Niagara — hydric soils 20.6% | 20.6 % | — | NRCS SSURGO — soil constraints by county | US federal work, public domain |
| Niagara County — 0.68 km to nearest mapped river | 0.68 km | 01 Nov 2026 | USA Rivers and Streams (distance per county) | Esri Living Atlas, derived from USGS NHD (public domain) |
| Globe Digital Holdings - 1 — AI data centre (192 MW) | 192 MW | 31 Aug 2026 | NYISO interconnection queue, including large loads | NYISO public interconnection queue — attribute NYISO |
| Wulf Compute Data Center II — AI data centre (250 MW) | 250 MW | 31 Aug 2026 | NYISO interconnection queue, including large loads | NYISO public interconnection queue — attribute NYISO |
| Lake Mariner Data II — AI data centre (250 MW) | 250 MW | 31 Aug 2026 | NYISO interconnection queue, including large loads | NYISO public interconnection queue — attribute NYISO |
| North East Data LLC Data Center — Data centre (500 MW) | 500 MW | 31 Aug 2026 | NYISO interconnection queue, including large loads | NYISO public interconnection queue — attribute NYISO |
| Niagara Digital Campus — Data centre (140 MW) | 140 MW | 31 Aug 2026 | NYISO interconnection queue, including large loads | NYISO public interconnection queue — attribute NYISO |
| GLOBE DH 2 — AI data centre (192 MW) | 192 MW | 31 Aug 2026 | NYISO interconnection queue, including large loads | NYISO public interconnection queue — attribute NYISO |
| Globe DH 3 — AI data centre (192 MW) | 192 MW | 31 Aug 2026 | NYISO interconnection queue, including large loads | NYISO public interconnection queue — attribute NYISO |
| Niagara County — 2.48 km to nearest natural-gas pipeline | 2.48 km | 01 Nov 2026 | EIA — natural gas pipelines (distance per county) | US federal work (EIA), public domain |
| Niagara County — 27 transmission substations (max 345 kV) | 27 substations | 01 Nov 2026 | HIFLD — transmission lines and substations | US federal work (HIFLD), public domain |
| Niagara County — 0.61 km to nearest 115 kV+ line | 0.61 km | 01 Nov 2026 | HIFLD — transmission lines and substations | US federal work (HIFLD), public domain |
| New York State Elec & Gas Corp serves Niagara County | New York State Elec & Gas Corp | 01 Jan 2025 | EIA-861 — utility service territory by county | US federal work, public domain |
| Niagara Mohawk Power Corp. serves Niagara County | Niagara Mohawk Power Corp. | 01 Jan 2025 | EIA-861 — utility service territory by county | US federal work, public domain |
| Niagara — expected annual loss $52.4m | 52,414,252.03 USD | — | FEMA National Risk Index | US federal work (FEMA), public domain |
| Niagara — NRI risk score 83.4 (Relatively Moderate) | 83.37 score | — | FEMA National Risk Index | US federal work (FEMA), public domain |
Derived figures — the band, readiness, studied share and comparisons — are CUDO derivations and say so wherever they appear.
Talk to us about Niagara County
Bring the site and the date. We will walk the evidence with you.