Lewis County, NY data center site data

Time to power, land, grid capacity, and risk for Lewis County, with a source and date for every figure.

Site summary

Lewis County time to power and site score

An estimated time-to-power band and a weighted site score summarize the county’s power access, queue readiness, gas access, land, and hazards.

Estimated time-to-power band
2–4 yrs
Readiness
Filed: no study complete

Top risks

  1. Most queued capacity here is speculative: under a third has a completed study.
  2. Top natural hazards (FEMA NRI): winter weather, inland flooding, hurricane.
Estimated site score, weighted
70/ 100
  • 35%Power access: 83 · max 230 kV substation; 2.2 km to a 115 kV+ line
  • 20%Queue readiness: 29 · 29.4% of queued MW has a completed study
  • 15%Gas access: 85 · 7.7 km to a gas pipeline
  • 15%Land available: 77 · 22.7% protected or public land
  • 15%Hazard: 75 · FEMA risk index 24.7
Land

Lewis County land availability and cost

Large parcels (100 acres or more), open land, land value per acre, protected land, floodplain, soil limits, brownfields, and water access for the county.

Parcels over 100 acres
2,174parcels
Industrial-class land
1,712acres
Vacant land value
$1,646
NYS Tax Parcels, county land aggregates · average assessed, per acre
Protected or public land
22.7%
Floodplain share
0%
Soil constraint
21% affected
NRCS SSURGO, soil constraints by county · Public domain · hydric 21.3% · shallow bedrock 17.6%
Brownfield sites
1sites
Distance to nearest river
0.1km
USA Rivers and Streams (distance per county) · Nov 1, 2026 · to nearest mapped river

Land cover

Share of classified land, from the USDA Cropland Data Layer.

forest63.09%
wetlands15%
grassland7.56%
cropland5.34%
developed3.47%
pasture hay2.4%
shrubland1.44%
water1.27%
barren0.44%
USDA CropScape, land cover by county · Public domain
Nearby data centers

Data centers in and near Lewis County

Operating data centers in the county and within 50 km, with their operators and distance from the county center.

Mapped data centers in county
0
Data centers within 50 km
0
Straight-line distance from the county center
Mapped footprint
0sq ft
IM3 Data Center Atlas (PNNL) · Nov 23, 2026 · ODbL 1.0 · no mapped data centre in this county
Projected future locations (IM3 model)
0locations
IM3, projected data-centre locations · Nov 23, 2026 · ODbL 1.0 · none projected here — IM3 model output, not announcements

No mapped data centre within 50 km of the county centre.

Mapped facilities are operating sites from the IM3 Atlas. Announced campuses not yet built come from Epoch AI and are not assigned to a county.

Risk

Lewis County natural hazard and permitting risk

FEMA hazard scores and disaster history, air-permitted data centers, local opposition, and ERCOT rule changes that apply to the county.

FEMA National Risk Index score
24.7score
FEMA National Risk Index · Public domain · Very Low
Expected annual loss
$9.1m
FEMA National Risk Index · Public domain
Disaster declarations since 2010
10
Air-permitted data centres
0facilities
none in this county · epa-echo-datacentre-air

Hazard scores

FEMA hazard risk scores, shown as national percentiles rather than the probability of loss at a site.

winter weather (Relatively Moderate)69
inland flooding (Relatively Low)50
hurricane (Very Low)47
earthquake (Very Low)47
strong wind (Relatively Low)33
tornado (Very Low)17
Power

Lewis County grid capacity and interconnection queue

Generation queued and operating in the county, transmission and gas access, power prices, and the NY-wide demand that new large loads compete with.

Generation and storage queue
425MW
Studied share of queue
125MW
29.4% of queued MW — derived from ISO status
Large-load queue
0MW
NYISO interconnection queue, including large loads · Oct 19, 2026 · no large load in the NYISO queue names this county
Operating generation
1,571MW
Transmission substations
13substations
HIFLD, transmission lines and substations · Nov 1, 2026 · Public domain · max 230 kV
Distance to 115 kV+ line
2.2km
HIFLD, transmission lines and substations · Nov 1, 2026 · Public domain · from county centre
Distance to gas pipeline
7.7km
EIA, natural gas pipelines (distance per county) · Nov 1, 2026 · Public domain · for on-site generation
Industrial power price
105.4$/MWh
EIA, industrial retail electricity price · Aug 1, 2026 · Public domain · state average
Grid peak and annual demand (NYISO)
31.1GW
eia-930-demand-profile · Nov 23, 2026 · peak hour, last 12 months · 151 TWh a year · ISO-wide, not this county
NY installed capacity above last year's peak
+38.4%
EIA, operating generator capacity by county · Aug 1, 2026 · Public domain · 43 GW installed vs 31.1 GW peak · firm only +18.3%
Queued MW per substation
33MW
NYISO interconnection queue, including large loads · 425 MW queued across 13 substations
Utilities serving the county
New York State Elec & Gas Corp · Niagara Mohawk Power Corp. · Village of Boonville - (NY)

Generation mix

Operating capacity by energy source.

WindNatural GasWaterSolar

Transmission substations

Substations at the ends of 115 kV and higher lines, from HIFLD.

SubstationkVOwner
Porter230NIAGARA MOHAWK POWER CORP.
Chases Lake230NIAGARA MOHAWK POWER CORP.
Chases Lake230NIAGARA MOHAWK POWER CORP.
Adirondack230NIAGARA MOHAWK POWER CORP.
Moose River115NIAGARA MOHAWK POWER CORP.
Boonville115NIAGARA MOHAWK POWER CORP.
Boonville115NIAGARA MOHAWK POWER CORP.
Taylorville115NIAGARA MOHAWK POWER CORP.
Moshier115NIAGARA MOHAWK POWER CORP.
Lyons Falls Hydroelectric115NIAGARA MOHAWK POWER CORP.
Local economy

Lewis County construction activity and data center jobs

Data processing and hosting businesses and jobs, and residential building permits as a measure of local construction activity.

Data processing and hosting locations
0establishments
Data processing and hosting jobs
0jobs
Residential units permitted
133permits
Census Building Permits Survey, county (residential) · Jan 1, 2025 · Public domain · Residential only; excludes data centers
Residential permit value
$30.9m
County map
Loading map…
Charts

Lewis County queue and demand charts

Queue in county by study stage

Active generation and storage, MW.

0 MW75 MW150 MW225 MW300 MWStudiedFiled

This county against the state median

Each figure as a multiple of the NY county median. 1.0 is typical.

Generation queue MW1.27×
Studied share0.29×
Transmission substations1.86×
Km to 115 kV+1.05×
Km to gas pipeline1.02×

Hourly demand profile (NY)

Average NY-wide demand by local hour over the last 15 days, MW.

0 GW5 GW9 GW14 GW18 GW000102030405060708091011121314151617181920212223eia-930-demand-profile · Nov 23, 2026

Queued MW in this county by expected online year

Active generation and storage requests, by the year each expects to connect.

0 MW75 MW150 MW225 MW300 MW20272030NYISO interconnection queue, including large loads
Sources

Sources for every Lewis County figure

FigureValueAs ofSourceLicense
Lewis County — 133 residential units permitted, 2025133 permits01 Jan 2025Census Building Permits Survey — county (residential)US federal work, public domain
Lewis County — $30,857,750 residential permit value, 202530,857,750 USD01 Jan 2025Census Building Permits Survey — county (residential)US federal work, public domain
Lewis — 1 brownfield sites1 sites—EPA — brownfield sites by countyUS federal work, public domain
36049 — pasture hay 2.4% of classified land (2025)2.4 %01 Jan 2025USDA CropScape — land cover by countyUS federal work, public domain
36049 — wetlands 15.0% of classified land (2025)15 %01 Jan 2025USDA CropScape — land cover by countyUS federal work, public domain
36049 — shrubland 1.44% of classified land (2025)1.44 %01 Jan 2025USDA CropScape — land cover by countyUS federal work, public domain
36049 — water 1.27% of classified land (2025)1.27 %01 Jan 2025USDA CropScape — land cover by countyUS federal work, public domain
36049 — forest 63.09% of classified land (2025)63.09 %01 Jan 2025USDA CropScape — land cover by countyUS federal work, public domain
36049 — barren 0.44% of classified land (2025)0.44 %01 Jan 2025USDA CropScape — land cover by countyUS federal work, public domain
36049 — cropland 5.34% of classified land (2025)5.34 %01 Jan 2025USDA CropScape — land cover by countyUS federal work, public domain
36049 — developed 3.47% of classified land (2025)3.47 %01 Jan 2025USDA CropScape — land cover by countyUS federal work, public domain
36049 — grassland 7.56% of classified land (2025)7.56 %01 Jan 2025USDA CropScape — land cover by countyUS federal work, public domain
36049 — data-centre employment (2025): 00 jobs01 Jan 2025BLS QCEW — data-centre establishments and jobs by countyBLS Quarterly Census of Employment and Wages (US federal work, public domain)
36049 — 0 data-centre establishments (2025)0 establishments01 Jan 2025BLS QCEW — data-centre establishments and jobs by countyBLS Quarterly Census of Employment and Wages (US federal work, public domain)
Lewis County — farmland $2,328 an acre (2022)2,328 USD per acre01 Jan 2022USDA Census of Agriculture — county land value and farm sizesUSDA NASS Census of Agriculture 2022 (US federal work, public domain)
Lewis County — 0.0% in FEMA's 1% annual-chance floodplain0 %—FEMA flood hazard areas — floodplain shareFEMA National Flood Hazard Layer (US federal work, public domain), served by Esri Living Atlas
Lewis — 1,712 acres in industrial property class1,712.4 acres—NYS Tax Parcels — county land aggregatesNYS ITS — aggregates only (owner names withheld)
Lewis County — 463 farms of 100+ acres (2022)463 farms01 Jan 2022USDA Census of Agriculture — county land value and farm sizesUSDA NASS Census of Agriculture 2022 (US federal work, public domain)
Lewis — average assessed value $1,646/acre, vacant land1,646 USD/acre—NYS Tax Parcels — county land aggregatesNYS ITS — aggregates only (owner names withheld)
Lewis — 2174 parcels of 100+ acres2,174 parcels—NYS Tax Parcels — county land aggregatesNYS ITS — aggregates only (owner names withheld)
Lewis County — 22.72% protected or public land22.72 %—USGS PAD-US — protected and public land shareUS federal work, public domain
Lewis — hydric soils 21.3%; shallow bedrock 17.6%21.3 %—NRCS SSURGO — soil constraints by countyUS federal work, public domain
Lewis County — 0.1 km to nearest mapped river0.1 km01 Nov 2026USA Rivers and Streams (distance per county)Esri Living Atlas, derived from USGS NHD (public domain)
Lewis County — 7.68 km to nearest natural-gas pipeline7.68 km01 Nov 2026EIA — natural gas pipelines (distance per county)US federal work (EIA), public domain
Lewis County — 13 transmission substations (max 230 kV)13 substations01 Nov 2026HIFLD — transmission lines and substationsUS federal work (HIFLD), public domain
Lewis County — 2.19 km to nearest 115 kV+ line2.19 km01 Nov 2026HIFLD — transmission lines and substationsUS federal work (HIFLD), public domain
New York State Elec & Gas Corp serves Lewis CountyNew York State Elec & Gas Corp01 Jan 2025EIA-861 — utility service territory by countyUS federal work, public domain
Village of Boonville - (NY) serves Lewis CountyVillage of Boonville - (NY)01 Jan 2025EIA-861 — utility service territory by countyUS federal work, public domain
Niagara Mohawk Power Corp. serves Lewis CountyNiagara Mohawk Power Corp.01 Jan 2025EIA-861 — utility service territory by countyUS federal work, public domain
Lewis — expected annual loss $9.1m9,139,545.25 USD—FEMA National Risk IndexUS federal work (FEMA), public domain
Lewis — NRI risk score 24.7 (Very Low)24.71 score—FEMA National Risk IndexUS federal work (FEMA), public domain

Derived figures — the band, readiness, studied share and comparisons — are CUDO derivations and say so wherever they appear.