Imperial County, CA data center site data
Time to power, land, grid capacity, and risk for Imperial County, with a source and date for every figure.
Imperial County time to power and site score
An estimated time-to-power band and a weighted site score summarize the county’s power access, queue readiness, gas access, land, and hazards.
- Readiness
- Interconnection agreement signed
Top risks
- Top natural hazards (FEMA NRI): earthquake, inland flooding, heat wave.
- 35%Power access: 100 · max 500 kV substation; 0.4 km to a 115 kV+ line
- 20%Queue readiness: 100 · 100.0% of queued MW has a completed study
- 15%Gas access: 98 · 0.9 km to a gas pipeline
- 15%Land available: 42 · 57.9% protected or public land
- 15%Hazard: 4 · FEMA risk index 96.5
Imperial County land availability and cost
Large parcels (100 acres or more), open land, land value per acre, protected land, floodplain, soil limits, brownfields, and water access for the county.
Land cover
Share of classified land, from the USDA Cropland Data Layer.
USDA CropScape, land cover by county · Public domainData centers in and near Imperial County
Operating data centers in the county and within 50 km, with their operators and distance from the county center.
No mapped data centre within 50 km of the county centre.
Mapped facilities are operating sites from the IM3 Atlas. Announced campuses not yet built come from Epoch AI and are not assigned to a county.
Imperial County natural hazard and permitting risk
FEMA hazard scores and disaster history, air-permitted data centers, local opposition, and ERCOT rule changes that apply to the county.
Hazard scores
FEMA hazard risk scores, shown as national percentiles rather than the probability of loss at a site.
Moratoriums, filings and opposition
- 08 Apr 2026
- 06 Nov 2025
- 07 May 2025
CA policy changes (statewide)
- 19 Nov 2026
- 14 Jul 2026
- 08 Jul 2026
- 21 Apr 2026
- 15 Jan 2026
Imperial County grid capacity and interconnection queue
Generation queued and operating in the county, transmission and gas access, power prices, and the CA-wide demand that new large loads compete with.
Generation mix
Operating capacity by energy source.
Transmission substations
Substations at the ends of 115 kV and higher lines, from HIFLD.
| Substation | kV | Owner |
|---|---|---|
| Imperial Valley | 500 | IMPERIAL IRRIGATION DISTRICT |
| Imperial Valley | 230 | SAN DIEGO GAS & ELECTRIC |
| Bannister | 230 | IMPERIAL IRRIGATION DISTRICT |
| El Centro | 230 | IMPERIAL IRRIGATION DISTRICT |
| Highline | 230 | IMPERIAL IRRIGATION DISTRICT |
| Imperial Valley | 230 | IMPERIAL IRRIGATION DISTRICT |
| Alhambra | 161 | IMPERIAL IRRIGATION DISTRICT |
| Blythe | 161 | IID |
| Niland | 161 | IMPERIAL IRRIGATION DISTRICT |
| El Centro | 161 | IMPERIAL IRRIGATION DISTRICT |
Imperial County construction activity and data center jobs
Data processing and hosting businesses and jobs, and residential building permits as a measure of local construction activity.
Imperial County queue and demand charts
Queue in county by study stage
Active generation and storage, MW.
This county against the state median
Each figure as a multiple of the CA county median. 1.0 is typical.
Hourly demand profile (CA)
Average CA-wide demand by local hour over the last 15 days, MW.
eia-930-demand-profile · Nov 22, 2026Queued MW in this county by expected online year
Active generation and storage requests, by the year each expects to connect.
No dated queue requests in this county.
Sources for every Imperial County figure
| Figure | Value | As of | Source | License |
|---|---|---|---|---|
| NOE 2026040352 — Lot Merger #00191 and vacation of Leimgruber Road | Lot Merger #00191 and vacation of Leimgruber Road | 08 Apr 2026 | CEQAnet — data center environmental filings | California public record (CEQAnet, State of California) |
| NOE 2025110216 — Grading Permit BP#63316 (Initial Study #25-0041) | Grading Permit BP#63316 (Initial Study #25-0041) | 06 Nov 2025 | CEQAnet — data center environmental filings | California public record (CEQAnet, State of California) |
| NOE 2025050253 — Two-Way Radio System Lifecycle Replacement Project (No. 200329) - Imperial Co. | Two-Way Radio System Lifecycle Replacement Project (No. 200329) - Imperial Co. | 07 May 2025 | CEQAnet — data center environmental filings | California public record (CEQAnet, State of California) |
| Imperial — 3 CEQA filings mentioning data centres since 2021 | 3 filings | 01 Jan 2021 | CEQAnet — data-centre filings per county | California public record (CEQAnet, State of California) |
| Imperial County — 242 residential units permitted, 2025 | 242 permits | 01 Jan 2025 | Census Building Permits Survey — county (residential) | US federal work, public domain |
| Imperial County — $38,908,029 residential permit value, 2025 | 38,908,029 USD | 01 Jan 2025 | Census Building Permits Survey — county (residential) | US federal work, public domain |
| Imperial — 6 brownfield sites | 6 sites | — | EPA — brownfield sites by county | US federal work, public domain |
| 06025 — developed 3.28% of classified land (2025) | 3.28 % | 01 Jan 2025 | USDA CropScape — land cover by county | US federal work, public domain |
| 06025 — pasture hay 2.1% of classified land (2025) | 2.1 % | 01 Jan 2025 | USDA CropScape — land cover by county | US federal work, public domain |
| 06025 — barren 32.04% of classified land (2025) | 32.04 % | 01 Jan 2025 | USDA CropScape — land cover by county | US federal work, public domain |
| 06025 — water 5.87% of classified land (2025) | 5.87 % | 01 Jan 2025 | USDA CropScape — land cover by county | US federal work, public domain |
| 06025 — wetlands 1.89% of classified land (2025) | 1.89 % | 01 Jan 2025 | USDA CropScape — land cover by county | US federal work, public domain |
| 06025 — grassland 0.45% of classified land (2025) | 0.45 % | 01 Jan 2025 | USDA CropScape — land cover by county | US federal work, public domain |
| 06025 — shrubland 40.53% of classified land (2025) | 40.53 % | 01 Jan 2025 | USDA CropScape — land cover by county | US federal work, public domain |
| 06025 — forest 0.01% of classified land (2025) | 0.01 % | 01 Jan 2025 | USDA CropScape — land cover by county | US federal work, public domain |
| 06025 — cropland 13.84% of classified land (2025) | 13.84 % | 01 Jan 2025 | USDA CropScape — land cover by county | US federal work, public domain |
| 06025 — data-centre employment (2025) — suppressed | suppressed for confidentiality | 01 Jan 2025 | BLS QCEW — data-centre establishments and jobs by county | BLS Quarterly Census of Employment and Wages (US federal work, public domain) |
| 06025 — 1 data-centre establishments (2025) | 1 establishments | 01 Jan 2025 | BLS QCEW — data-centre establishments and jobs by county | BLS Quarterly Census of Employment and Wages (US federal work, public domain) |
| Imperial County — farmland $11,892 an acre (2022) | 11,892 USD per acre | 01 Jan 2022 | USDA Census of Agriculture — county land value and farm sizes | USDA NASS Census of Agriculture 2022 (US federal work, public domain) |
| Imperial County — 13.24% in FEMA's 1% annual-chance floodplain | 13.24 % | — | FEMA flood hazard areas — floodplain share | FEMA National Flood Hazard Layer (US federal work, public domain), served by Esri Living Atlas |
| Imperial County — 665 farms of 100+ acres (2022) | 665 farms | 01 Jan 2022 | USDA Census of Agriculture — county land value and farm sizes | USDA NASS Census of Agriculture 2022 (US federal work, public domain) |
| Imperial County — 57.93% protected or public land | 57.93 % | — | USGS PAD-US — protected and public land share | US federal work, public domain |
| Imperial — shallow bedrock 25.1% | 25.1 % | — | NRCS SSURGO — soil constraints by county | US federal work, public domain |
| Imperial County — 4.79 km to nearest mapped river | 4.79 km | 01 Nov 2026 | USA Rivers and Streams (distance per county) | Esri Living Atlas, derived from USGS NHD (public domain) |
| Imperial County — 0.94 km to nearest natural-gas pipeline | 0.94 km | 01 Nov 2026 | EIA — natural gas pipelines (distance per county) | US federal work (EIA), public domain |
| Imperial County — 14 transmission substations (max 500 kV) | 14 substations | 01 Nov 2026 | HIFLD — transmission lines and substations | US federal work (HIFLD), public domain |
| Imperial County — 0.36 km to nearest 115 kV+ line | 0.36 km | 01 Nov 2026 | HIFLD — transmission lines and substations | US federal work (HIFLD), public domain |
| WAPA-- Western Area Power Administration serves Imperial County | WAPA-- Western Area Power Administration | 01 Jan 2025 | EIA-861 — utility service territory by county | US federal work, public domain |
| Southern California Edison Co serves Imperial County | Southern California Edison Co | 01 Jan 2025 | EIA-861 — utility service territory by county | US federal work, public domain |
| Imperial Irrigation District serves Imperial County | Imperial Irrigation District | 01 Jan 2025 | EIA-861 — utility service territory by county | US federal work, public domain |
| Imperial — expected annual loss $147.6m | 147,566,579.84 USD | — | FEMA National Risk Index | US federal work (FEMA), public domain |
| Imperial — NRI risk score 96.5 (Relatively High) | 96.47 score | — | FEMA National Risk Index | US federal work (FEMA), public domain |
Derived figures — the band, readiness, studied share and comparisons — are CUDO derivations and say so wherever they appear.